Difference between revisions of "Fall 2014 Commissioning Plan"

From Hall D Ops Wiki
Jump to: navigation, search
(Tune Electron Beam#Tune Electron Beam)
Line 17: Line 17:
 
** Running data at 1350A solenoid current.
 
** Running data at 1350A solenoid current.
 
=Run Plan=
 
=Run Plan=
==[[Tune Electron Beam#Tune Electron Beam]]==
+
==[[Tune Electron Beam#Tune Electron Beam Tune Electron Beam]]==
 +
 
 
==[[Tune Photon Beam#Tune Photon Beam]]==
 
==[[Tune Photon Beam#Tune Photon Beam]]==
 
==[[One Week Pause in Running#One Week Pause in Running]]==
 
==[[One Week Pause in Running#One Week Pause in Running]]==

Revision as of 12:58, 2 July 2014

General Information

  • Expected Staffing:
    • Run Coordinator: To be named
    • Online Shifts: 3 persons per shift, one with solenoid training.
    • Offline Shifts: at least two people looking at data written to tape.
  • Coordination Activities:
    • MCC meeting at 7:00am
    • Daily run meeting broadcast on bluejeans 10:30am??
  • Activity Priority
    • High: Activity should be completed, contingencies in place for issues.
    • Medium: Desirable to complete the activity.
    • Low: Activity would be useful if time permits us to do it.
  • Deferred Activity
    • Installation of liquid hydrogen target.
    • Installation of diamond radiator in goniometer.
    • Running data at 1350A solenoid current.

Run Plan

Tune Electron Beam#Tune Electron Beam Tune Electron Beam

Tune Photon Beam#Tune Photon Beam

One Week Pause in Running#One Week Pause in Running

Collect Beam Data for Detector Checkout#Collect Beam Data for Detector Checkout

Optimize Detector Settings#Optimize Detector Settings

Drift Chamber Alignment#Drift Chamber Alignment

Collect More Regular Data#Collect More Regular Data