Difference between revisions of "Fall 2014 Commissioning Plan"

From Hall D Ops Wiki
Jump to: navigation, search
(General Information)
(General Information)
Line 4: Line 4:
 
** Commissioning of the unpolarized photon beam
 
** Commissioning of the unpolarized photon beam
 
** Commissioning of the Hall D equipment under "soft" conditions:
 
** Commissioning of the Hall D equipment under "soft" conditions:
*** low-intensity unpolarized photon beam <10 MHz/GeV  
+
*** low-intensity unpolarized photon beam <10 MHz/GeV at the endpoint
 
*** thin solid targets instead of the regular liquid hydrogen target
 
*** thin solid targets instead of the regular liquid hydrogen target
 
*** solenoid current 1200 A instead of the nominal 1300 A
 
*** solenoid current 1200 A instead of the nominal 1300 A

Revision as of 19:24, 5 August 2014

General Information

  • Goals
    • Commissioning of the unpolarized photon beam
    • Commissioning of the Hall D equipment under "soft" conditions:
      • low-intensity unpolarized photon beam <10 MHz/GeV at the endpoint
      • thin solid targets instead of the regular liquid hydrogen target
      • solenoid current 1200 A instead of the nominal 1300 A
  • Schedule
    • Accelerator: beam recovery and 5.5 pass beam tune to the Tagger Dump (see [1]) are scheduled for Sept 19 - Oct 3
    • Photon beam tune and Hall D commissioning are scheduled for 3 weeks between 10-Oct and 22-Dec 2014 (tentatively 10-31 Oct)
  • Expected Staffing:
    • Run Coordinator: Alexandre Deur
    • Online Shifts: 3 persons per shift, one with solenoid training.
    • Offline Shifts: at least two people looking at data written to tape.
  • Coordination Activities:
  • Activity Priority
    • High: Activity should be completed, contingencies in place for issues.
    • Medium: Desirable to complete the activity.
    • Low: Activity would be useful if time permits us to do it.
  • Activities postponed to the next run
    • Installation of liquid hydrogen target.
    • Installation of diamond radiator in goniometer.
    • Running data at 1300A solenoid current.

Beam Configuration Parameters

  • Energy of Beam. Expect energy ~ 10.5 GeV
  • Beam current
    • 2-10 µA pulsed beam, duty cycle 1.5% (see beam description here)
    • 50-200 nA CW
  • Radiators
    • 1.5 microns Al (1.7·10-5 R.L.)
    • 10 microns Al (11.·10-5 R.L.)
    • 30 microns Al (34.·10-5 R.L.)
  • Targets. Diameter = 3.19 cm. The position of the target can be moved 12 cm downstream to 32 cm upstream relative to the nominal Hall D target position (60 cm downstream of the downstream end of the upstream solenoid endcap.)
    • 10mm thick disk of CH2 (HDPE, high density polyethylene, density 0.93-0.97 g/cm3 )
    • 2mm thick disk CH2 (HDPE)
    • 2mm thick for the 2mm-inner diameter and 7mm thick outside (HDPE)
    • 3.4mm thick graphite disk
  • Run schedule. Scheduled about 4 weeks of beam to Hall D between mid Oct and mid Dec, 2014

Run Plan

Tune Electron Beam

Tune Photon Beam

One Week Pause in Running

Collect Beam Data for Detector Checkout

Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data