Fall 2014 Commissioning Plan

From Hall D Ops Wiki
Revision as of 16:37, 7 July 2014 by Elton (Talk | contribs) (Beam Configuration Parameters)

Jump to: navigation, search

General Information

  • Expected Staffing:
    • Run Coordinator: To be named
    • Online Shifts: 3 persons per shift, one with solenoid training.
    • Offline Shifts: at least two people looking at data written to tape.
  • Coordination Activities:
    • MCC meeting at 7:00am
    • Daily run meeting broadcast on bluejeans 10:30am??
  • Activity Priority
    • High: Activity should be completed, contingencies in place for issues.
    • Medium: Desirable to complete the activity.
    • Low: Activity would be useful if time permits us to do it.
  • Deferred Activity
    • Installation of liquid hydrogen target.
    • Installation of diamond radiator in goniometer.
    • Running data at 1350A solenoid current.

Beam Configuration Parameters

  • Energy of Beam. Expect energy ~ 10.5 GeV
  • Current of Beam
    • 4-10 microA with pulsed beam
    • 100-400 nA cw
  • Radiators
    • 0.8 microns Al (0.9 x 10^-5 rad len)
    • 30 microns Al (3.4 x 10^-4 rad len)
    • 100 microns Al (1.1 x 10^-3 rad len)
  • Targets. Diameter = 3.19 cm. The position of the target can be moved 12 cm downstream to 32 cm upstream relative to the nominal Hall D target position (60 cm downstream of the downstream end of the upstream solenoid endcap.)
    • 10mm disk of CH2 (HDPE, high density polyethylene)
    • 2mm disk CH2 (HDPE)
    • CH2 (HDPE) cup of 2mm thickness for the 2mm-inner diameter and 7mm for the outer ring.
    • 3.4mm C12 graphite disk
  • Run schedule. Scheduled about 4 weeks of beam to Hall D between mid Oct and mid Dec, 2014

Run Plan

Tune Electron Beam

Tune Photon Beam

One Week Pause in Running

Collect Beam Data for Detector Checkout

Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data