Difference between revisions of "One Week Pause in Running"

From Hall D Ops Wiki
Jump to: navigation, search
(Main Page)
(One Week Pause in Running)
Line 7: Line 7:
 
# Goal: Reinstall tagger detectors/electronics and check data.
 
# Goal: Reinstall tagger detectors/electronics and check data.
 
# Responsibility: HallD
 
# Responsibility: HallD
 +
# Priority: High
 
# Conditions:
 
# Conditions:
 
#* Beam off in the Hall.
 
#* Beam off in the Hall.

Revision as of 14:26, 2 July 2014

Main Page

Tune Electron Beam

Tune Photon Beam

One Week Pause in Running

  1. Goal: Reinstall tagger detectors/electronics and check data.
  2. Responsibility: HallD
  3. Priority: High
  4. Conditions:
    • Beam off in the Hall.
  5. Acivities
    • Reinstall the tagger detector, TAGM and the electronics, reconnect the cables.
    • Check validity of data offline. Use as feedback to detector settings.
    • Check/modify the online monitoring histograms based on data.

Collect Beam Data for Detector Checkout

Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data