Revision as of 12:11, 2 July 2014
Contents
Main Page
Tune Electron Beam
Tune Photon Beam
One Week Pause in Running
- Goal: Reinstall tagger detectors/electronics and check data.
- Responsibility: HallD
- Conditions:
- Beam off in the Hall.
- Acivities
- Reinstall the tagger detector, TAGM and the electronics, reconnect the cables.
- Check validity of data offline. Use as feedback to detector settings.
- Check/modify the online monitoring histograms based on data.