(Created page with "'''This page gives the run plan for the Fall 2014 commissioning. It is a controlled document that can be edited only by E. Chudakov, E. Smith or A. Deur. Suggestions and comme...")
 
Line 1: Line 1:
'''This page gives the run plan for the Fall 2014 commissioning. It is a controlled document that can be edited only by E. Chudakov, E. Smith or A. Deur. Suggestions and comments should be send to them.
+
'''This page gives the run plan for the Spring 2015 commissioning. It is a controlled document that can be edited only by E. Chudakov, E. Smith or A. Deur. Suggestions and comments should be send to them.
 
'''
 
'''
  
Line 6: Line 6:
 
=General Information=
 
=General Information=
  
This document describes the run plan and procedures for the Hall D Fall 2014 commissioning.  
+
This document describes the run plan and procedures for the Hall D spring 2015 commissioning.  
  
* Goals for the Fall 2014 run (expected durations are given in parenthesis)
+
* Schedule for the Spring 2015 run. (Dates are according to the [https://www.jlab.org/exp_prog/experiment_schedule/2014/Oct14-Dec15_M&S_20141001.pdf October 2014 - December 2015 Memo and Schedule (20141001)]. They will be updated if necessary in the [https://halldweb1.jlab.org/wiki/index.php/Run_Coordination_Meetings#Meeting_General_Agenda run coordination meeting pages])
*# See start dates in the run coordination meeting pages [https://halldweb1.jlab.org/wiki/index.php/Run_Coordination_Meetings#Meeting_General_Agenda here]
+
*# Feb. 13 - Feb. 26: Beam restoration (13 days)
*# Clean tune of the electron beam into the Tagger Dump (13 days)
+
*# Feb. 27 - March 26: Accelerator development. Physics running conditions are similar to Fall 2014: <span style="color:red">Accelerator has priority.</span> Possible running for Halls A/B/D.
*# Commissioning of the unpolarized photon beam (4 days)
+
*# Apr. 3 - May 4: Physics run (Halls A/B/D).
*# Reinstall Tagger electronics (6 days)
+
* Goals for the Spring 2015 run.
*# Commissioning of the Hall D equipment under "soft" conditions (17 days):
+
*# Commission the new Hall D equipment:
*#* Low-intensity unpolarized photon beam <10 MHz/GeV at the endpoint
+
***LH2 target, high priority.  (<span style="color:fuchsia"> Expected time ?? </span>)  
*#* Thin solid targets instead of the regular liquid hydrogen target
+
***Diamond radiator/goniometer, high priority.  (<span style="color:fuchsia"> Expected time ?? </span>)
*#* Solenoid current 1200 A instead of the nominal 1300 A
+
***Accelerator clock, low priority.  (<span style="color:fuchsia"> Expected time ?? </span>)
* Schedule and Hall Availability: The tentative plan is:
+
***Total Absorption Counter (TAC), low priority.  (<span style="color:fuchsia"> Expected time ?? </span>)
*# Accelerator: beam recovery and 5.5 pass beam tune to the dumplette Oct 08-17. Hall D/Tagger are open.
+
***Photon beam polarimeter, low priority. (<span style="color:fuchsia"> Expected time ?? </span>)
*# Accelerator: electron beam tune to the Tagger Dump, 17-oct-14 - 21-Oct-14. Hall D/Tagger are locked. TAGM and the electronics are removed from the Tagger Hall.
+
*# Establish DAQ operation in Block Mode with ~ 20 kHz rate.
*# Accelerator/Hall D: Photon beam tune to Hall D and the initial equipment checkout, Oct 22-26. Halls are locked.  
+
*# Complete detector calibration/alignment.
*# Hall D: Re-installation of the Tagger equipment (TAGM and the electronics), Oct 27- Nov 02. Halls are open.
+
*# Complete trigger optimization.
*# Hall D: Equipment commissioning with photon beam, Nov 03-18. Halls are locked.
+
*# Commission beam stability feedbacks.  
 
* Expected Staffing and responsibilities:  
 
* Expected Staffing and responsibilities:  
 
**The Run Coordinator (RC, Alexandre Deur) oversees the commissioning.  
 
**The Run Coordinator (RC, Alexandre Deur) oversees the commissioning.  
**<span style="color:black">The Physics Division Liaison (PDL, Yi Qiang) </span> and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed.  
+
**The Physics Division Liaison (PDL, <span style="color:fuchsia">TBD </span>) and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed.  
**The Analysis Coordinator (Paul Mattione)  will organize the off-line analysis effort.  
+
**The Analysis Coordinator (<span style="color:fuchsia">TBD</span>)  will organize the off-line analysis effort.  
 
**Individuals responsible for each commissioning step are named in the section describing the step. They are also responsible for logging in the ELog the summary of how the step proceeded and other relevant information.  
 
**Individuals responsible for each commissioning step are named in the section describing the step. They are also responsible for logging in the ELog the summary of how the step proceeded and other relevant information.  
 
**Shifts
 
**Shifts
*** Online Shifts (Nominally 2 persons per shift, one with solenoid training.): 
+
*** 2 persons per shift, one with solenoid training
**** Electron beam commissioning: Shifts will be scheduled but be stand-by shifts by default. The counting room will be manned only if accelerator needs a contact, or if Hall D expertise is needed to support the beam tuning (e.g. to operate the amorphous collimator harp). If so, the shift leader will be asked to be present. If the task demands it, the two-man rule must be obeyed.
+
**** Photon beam commissioning: Only beam line equipment and the solenoid will be operated. The detectors will be turned off for most of the time, with the possible exception of BCAL and the outer rings of FCAL. The counting room will be manned by two shift persons, one with solenoid training, and the experts necessary to the conduct of specific parts of the run plan. The RC will assign the experts. The third shift taker will be on stand-by.
+
**** Initial detector testing with the tagger equipment still removed: Once the photon beam is commissioned the Hall D detectors will be turned on, Online shifts will be operated by three persons, one with solenoid training.
+
**** Re-installation of the tagger equipment: Shifts are on stand-by.
+
**** Detector commissioning : Online shifts will be operated by three persons, one with solenoid training.
+
*** Offline Shifts: None.
+
 
* Coordination Activities:
 
* Coordination Activities:
 
** The RC will attend the MCC meetings at 7:50am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
 
** The RC will attend the MCC meetings at 7:50am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
** Daily run meetings broadcasted on Bluejeans will occur at 10:30am in the counting house conference room. The Analysis Coordinator will be responsible for organizing and chairing the meeting.  
+
** Daily run meetings broadcasted on Bluejeans will occur at 10:30am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.  
** Links to accelerator schedules:
+
* Useful links:
 +
**Accelerator schedule
 
***[http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/Fall2014.html CEBAF 12 GeV Commissioning calendar]
 
***[http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/Fall2014.html CEBAF 12 GeV Commissioning calendar]
 
***[https://accweb.acc.jlab.org/calendar/  Scheduled Accelerator Down (SAD)/Maintenance Calendar]
 
***[https://accweb.acc.jlab.org/calendar/  Scheduled Accelerator Down (SAD)/Maintenance Calendar]
Line 48: Line 43:
 
***[https://www.jlab.org/accel/RadCon/opsgraphs/72h/halld_72h.pdf Same but Last 72-hours]
 
***[https://www.jlab.org/accel/RadCon/opsgraphs/72h/halld_72h.pdf Same but Last 72-hours]
 
***Week, month, and quarter (3 months) plots also exist, with similar web addresses.
 
***Week, month, and quarter (3 months) plots also exist, with similar web addresses.
*** A map of the radiation monitors [[File:rad_det_map.jpg | 100px]]
+
*** A map of the radiation monitors [[File:Location_detect2.jpg | 100px]]
* Activity Priority
+
** High: Activity should be completed, contingencies in place for issues.
+
** Medium: Desirable to complete the activity.
+
** Low: Activity would be useful if time permits us to do it.
+
* Activities planned for the next run in Spring 2015:
+
** Installation and operations of the liquid hydrogen target.
+
** Installation and operation of diamond radiators in goniometer.
+
** Running at 1300A solenoid current.
+
  
 
= Beam Configuration Parameters =
 
= Beam Configuration Parameters =
*  Energy of Beam: expected ~ 10.1 GeV
+
*  Energy of Beam: expected ~ 11 GeV
* Beam current:
+
* Solenoid current up to 1300A (running condition).
** Electron beam tuning is done with pulsed beam 4-10 &micro;A, duty cycle 1.5%, average current 60-150nA (see the tune beam description [https://halldweb1.jlab.org/wiki/index.php/Tune_mode here])
+
* Beam current for Photon beam operations: CW 50 na-1 μA.
** Photon beam operations: CW 50-200 nA
+
* Radiators:  
* Radiators:
+
** Nominal: Diamond.
** 1.5 &micro;m Al (1.7&middot;10<sup>-5</sup> R.L.)
+
** Other available:
** 10 &micro;m Al (11.2&middot;10<sup>-5</sup> R.L.)
+
*** 1.5 &micro;m Al (1.7&middot;10<sup>-5</sup> R.L.)
** 30 &micro;m Al (33.7&middot;10<sup>-5</sup> R.L.)
+
*** 10 &micro;m Al (11.2&middot;10<sup>-5</sup> R.L.)
* Collimator hole: 5 mm diameter
+
*** 30 &micro;m Al (33.7&middot;10<sup>-5</sup> R.L.)
* The commissioning targets are disks of 3.19 cm diameter. Only one disk can be installed at a time. The z-position of a disk can be moved 12 cm downstream to 32 cm upstream relative to the nominal Hall D cryotarget center (60 cm downstream of the downstream end of the upstream solenoid end-cap). The available disks are:
+
* Collimator hole: 5 mm diameter nominally. May run on the 3.4 mm once priority plans are completed.  
**  10mm thick disk of CH<sub>2</sub> (HDPE, high density polyethylene, density 0.93-0.97 g/cm<sup>3</sup> ), 0.95 g/cm<sup>2</sup>, ~1.2% R.L.
+
* Main target: LH2 [https://hdops.jlab.org/wiki/index.php/Cryogenic_Target_Shift cryogenic target] 
** 2mm thick disk CH<sub>2</sub> (HDPE)
+
** Backup targets are are:
** 2mm thick inside a 20mm diameter area and 7mm thick outside (HDPE)
+
***  10mm thick disk (3.19 cm diameter) of CH<sub>2</sub> (HDPE, high density polyethylene, density 0.93-0.97 g/cm<sup>3</sup> ), 0.95 g/cm<sup>2</sup>, ~1.2% R.L.
** 3.4mm thick graphite disk, 0.75 g/cm<sup>2</sup>, 1.8% R.L.
+
*** 2mm thick disk (3.19 cm diameter) CH<sub>2</sub> (HDPE)
** Al. cross made of 1.59 mm diameter wires
+
*** 2mm thick inside a 20mm diameter area and 7mm thick outside (HDPE)
** 1cm long Al. cylinder with an equilateral triangle hole inside. The triangle edge lengths are 2.5 cm
+
*** 3.4mm thick graphite (3.19 cm diameter) disk, 0.75 g/cm<sup>2</sup>, 1.8% R.L.
 +
*** Al. cross made of 1.59 mm diameter wires
 +
*** 1cm long Al. cylinder with an equilateral triangle hole inside. The triangle edge lengths are 2.5 cm
  
 
=Run Plan=
 
=Run Plan=

Revision as of 10:32, 12 January 2015

This page gives the run plan for the Spring 2015 commissioning. It is a controlled document that can be edited only by E. Chudakov, E. Smith or A. Deur. Suggestions and comments should be send to them.

Items in pink indicate missing information.

General Information

This document describes the run plan and procedures for the Hall D spring 2015 commissioning.

  • Schedule for the Spring 2015 run. (Dates are according to the October 2014 - December 2015 Memo and Schedule (20141001). They will be updated if necessary in the run coordination meeting pages)
    1. Feb. 13 - Feb. 26: Beam restoration (13 days)
    2. Feb. 27 - March 26: Accelerator development. Physics running conditions are similar to Fall 2014: Accelerator has priority. Possible running for Halls A/B/D.
    3. Apr. 3 - May 4: Physics run (Halls A/B/D).
  • Goals for the Spring 2015 run.
    1. Commission the new Hall D equipment:
      • LH2 target, high priority. ( Expected time ?? )
      • Diamond radiator/goniometer, high priority. ( Expected time ?? )
      • Accelerator clock, low priority. ( Expected time ?? )
      • Total Absorption Counter (TAC), low priority. ( Expected time ?? )
      • Photon beam polarimeter, low priority. ( Expected time ?? )
    1. Establish DAQ operation in Block Mode with ~ 20 kHz rate.
    2. Complete detector calibration/alignment.
    3. Complete trigger optimization.
    4. Commission beam stability feedbacks.
  • Expected Staffing and responsibilities:
    • The Run Coordinator (RC, Alexandre Deur) oversees the commissioning.
    • The Physics Division Liaison (PDL, TBD ) and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed.
    • The Analysis Coordinator (TBD) will organize the off-line analysis effort.
    • Individuals responsible for each commissioning step are named in the section describing the step. They are also responsible for logging in the ELog the summary of how the step proceeded and other relevant information.
    • Shifts
      • 2 persons per shift, one with solenoid training
  • Coordination Activities:
    • The RC will attend the MCC meetings at 7:50am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
    • Daily run meetings broadcasted on Bluejeans will occur at 10:30am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
  • Useful links:

Beam Configuration Parameters

  • Energy of Beam: expected ~ 11 GeV
  • Solenoid current up to 1300A (running condition).
  • Beam current for Photon beam operations: CW 50 na-1 μA.
  • Radiators:
    • Nominal: Diamond.
    • Other available:
      • 1.5 µm Al (1.7·10-5 R.L.)
      • 10 µm Al (11.2·10-5 R.L.)
      • 30 µm Al (33.7·10-5 R.L.)
  • Collimator hole: 5 mm diameter nominally. May run on the 3.4 mm once priority plans are completed.
  • Main target: LH2 cryogenic target
    • Backup targets are are:
      • 10mm thick disk (3.19 cm diameter) of CH2 (HDPE, high density polyethylene, density 0.93-0.97 g/cm3 ), 0.95 g/cm2, ~1.2% R.L.
      • 2mm thick disk (3.19 cm diameter) CH2 (HDPE)
      • 2mm thick inside a 20mm diameter area and 7mm thick outside (HDPE)
      • 3.4mm thick graphite (3.19 cm diameter) disk, 0.75 g/cm2, 1.8% R.L.
      • Al. cross made of 1.59 mm diameter wires
      • 1cm long Al. cylinder with an equilateral triangle hole inside. The triangle edge lengths are 2.5 cm

Run Plan

Commissioning time chart:
Commissioning time chart. Time t=0 corresponds to the Hall being locked-up for beam tunning. With the present schedule, it is sometime in the first half of Oct. The horizontal scale is the time during which beam is available (in other word, it would be the real time with 100% of beam efficiency). The task time estimates given on the plot have 100% contingency.

Tune Electron Beam

Tune Photon Beam and collect data for initial detector checkout

One Week Pause in Running

Finalize Photon Beam Commissioning and Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data

Post-thanksgiving period