(Tune Electron Beam (Time estimate: 15 days))
(Tune Electron Beam (Time estimate: 15 days))
Line 10: Line 10:
 
# Sept 29 - Oct 3 2014:  Tune beam to Tagger Hall D  (Tagger Hall and Hall D must be closed).  
 
# Sept 29 - Oct 3 2014:  Tune beam to Tagger Hall D  (Tagger Hall and Hall D must be closed).  
 
* Prerequisites:
 
* Prerequisites:
# Tagger microscope (TAGM) and all the crates with electronics should be removed from Hall D.
+
# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <math>\Box</math>
#* Responsibility: Hall D technical staff/Tom Carstens <math>\Box</math>
+
 
# Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span>
 
# Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span>
# Amorphous radiator ladder equipped (HARP included) and operational
+
# Amorphous radiator ladder equipped (HARP included) and operational <math>\Box</math>
#* Responsibility: Hovanes Egiyan. <math>\Box</math>
+
#* Responsibility: Hovanes Egiyan.
 
#* <span style="color:#ff00ff">Procedure for radiator harp scans </span>
 
#* <span style="color:#ff00ff">Procedure for radiator harp scans </span>
# Beam lines under vacuum
+
# Beam lines under vacuum <math>\Box</math>
# Tagger magnet operational
+
# Tagger magnet operational <math>\Box</math>
# Shielding walls installed
+
#* Responsibility: MCC
# Radiation monitors installed and operational
+
# Shielding walls installed <math>\Box</math>
# Primary collimator block in the position between two holes, shielding the central area of the beam pipe. Secondary collimator removed.
+
# Radiation monitors installed and operational <math>\Box</math>
# Profiler counter installed in front of the collimator
+
#* Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
 +
#* <span style="color:#ff00ff">Procedure to monitor CARMs </span>
 +
#* <span style="color:#ff00ff">Procedure to Halo counters </span>
 +
# Primary collimator block in the position between two holes, shielding the central area of the beam pipe <math>\Box</math>. Secondary collimator removed. <span style="font-size:21px">☑</span>
 +
#* Responsibility: Hovanes Egiyan.
 +
#* <span style="color:#ff00ff">Procedure for moving Primary Collimator </span>
 +
# First Profiler counter installed in front of the collimator <math>\Box</math>
 +
# Second Profiler counter installed in front of photon beam dump <math>\Box</math>
  
 
* Conditions:
 
* Conditions:
 
# Pulsed beam [https://halldweb1.jlab.org/wiki/index.php/Tune_mode pulsed beam] 4-10 &micro;A (average 60-150 nA) for the beam tune
 
# Pulsed beam [https://halldweb1.jlab.org/wiki/index.php/Tune_mode pulsed beam] 4-10 &micro;A (average 60-150 nA) for the beam tune
 
# CW beam 50-100 nA at the final stage of the procedure  
 
# CW beam 50-100 nA at the final stage of the procedure  
# No radiator
+
# No radiator inserted. <math>\Box</math>
# Hall D quadrupole magnet MQPAD00 turned off
+
#* Responsibility: Hovanes Egiyan.
# Hall D/Tagger Hall locked
+
#* <span style="color:#ff00ff">Procedure for inserting amorphous radiator </span>
# No shift workers in Hall D; experts from Hall D are involved with the radiation measurements
+
# Hall D controlled quadrupole MQPAD00 turned off. <math>\Box</math>
 +
#* Responsibility: MCC
 +
# No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements
  
 
* Activities:
 
* Activities:

Revision as of 10:53, 14 August 2014

Main Page

Tune Electron Beam (Time estimate: 15 days)

  1. Sept 19 - Sept 29: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
  2. Sept 29 - Oct 3 2014: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
  • Prerequisites:
  1. Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. \Box
  2. Goniometer in the beam-open position. The goniometer will not be used during the 2014 run.
  3. Amorphous radiator ladder equipped (HARP included) and operational \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for radiator harp scans
  4. Beam lines under vacuum \Box
  5. Tagger magnet operational \Box
    • Responsibility: MCC
  6. Shielding walls installed \Box
  7. Radiation monitors installed and operational \Box
    • Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
    • Procedure to monitor CARMs
    • Procedure to Halo counters
  8. Primary collimator block in the position between two holes, shielding the central area of the beam pipe \Box . Secondary collimator removed.
    • Responsibility: Hovanes Egiyan.
    • Procedure for moving Primary Collimator
  9. First Profiler counter installed in front of the collimator \Box
  10. Second Profiler counter installed in front of photon beam dump \Box
  • Conditions:
  1. Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
  2. CW beam 50-100 nA at the final stage of the procedure
  3. No radiator inserted. \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for inserting amorphous radiator
  4. Hall D controlled quadrupole MQPAD00 turned off. \Box
    • Responsibility: MCC
  5. No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements
  • Activities:
  1. Tune the pulsed beam to the dump, check the beam specifications, send the CW beam (accelerator).
  2. Check radiation levels in the tagger hall (Hall D/RadCon).
  3. Check for photons (with the Profiler and Active Collimator) and radiation levels in the collimator cave (Hall D/RadCon).
  • Responsibility: Main: Accelerator; support: HallD, RadCon.

Tune Photon Beam

One Week Pause in Running

Collect Beam Data for Detector Checkout

Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data