(Tune Electron Beam (Time estimate: 15 days))
(Tune Electron Beam (Time estimate: 15 days))
Line 37: Line 37:
 
# Hall D controlled quadrupole MQPAD00 turned off. <math>\Box</math>
 
# Hall D controlled quadrupole MQPAD00 turned off. <math>\Box</math>
 
#* Responsibility: MCC
 
#* Responsibility: MCC
# No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements
+
# No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements. RC and/or other Hall D personnel follows the beam tunning procedure at the MCC.
  
 
==[[Tune Photon Beam]]==
 
==[[Tune Photon Beam]]==

Revision as of 12:16, 19 August 2014

Main Page

Tune Electron Beam (Time estimate: 15 days)

  1. Sept 19 - Sept 29: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
  2. Sept 29 - Oct 3 2014: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
  • Prerequisites:
  1. Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. \Box
  2. Goniometer in the beam-open position. The goniometer will not be used during the 2014 run.
  3. Amorphous radiator ladder equipped (HARP included) and operational \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for radiator harp scans
  4. Beam lines under vacuum \Box
  5. Tagger magnet operational \Box
    • Responsibility: MCC
  6. Shielding walls installed \Box
  7. Radiation monitors installed and operational \Box
    • Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
    • Procedure to monitor CARMs
    • Procedure to monitor Halo Counters
  8. Primary collimator block in the position between two holes, shielding the central area of the beam pipe \Box . Secondary collimator removed.
    • Responsibility: Hovanes Egiyan.
    • Procedure for moving Primary Collimator
  9. First Profiler counter installed in front of the collimator \Box
  10. Second Profiler counter installed in front of photon beam dump \Box
  • Conditions:
  1. Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
  2. CW beam 50-100 nA at the final stage of the procedure
  3. No radiator inserted. \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for inserting/removing amorphous radiators
  4. Hall D controlled quadrupole MQPAD00 turned off. \Box
    • Responsibility: MCC
  5. No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements. RC and/or other Hall D personnel follows the beam tunning procedure at the MCC.

Tune Photon Beam

One Week Pause in Running

Collect Beam Data for Detector Checkout

Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data