Coil Test Weekly Meeting 24-Jun-2011
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Fri 24-Jun-2011 9:30 am ARC 231
Agenda
- Close out P6 solenoid equipment task
- Coil 2 status
- installation status
- cooldown timeline
- subcoil inductances and quench detector
- Floyd's spreadsheet for modified taps lists inductance for 2 a,b,c,d: 1.08501, 0.6312, 0.66625, 0.92144 H
- in pairs you get 1.71 and 1.59, ratio about 1.08
- will we use one or two QD channels?
- Danfysik fault sequencer and slow dump
- additional PLC and HMI programming
- network loss problem
- auto elog entries failure
- fast DAQ
- replace smaller UPS
- anything else?
- Documentation
- trip chains
- anything else?
- Auxiliar tests
- Beni wants to do more crate tests
- To-do list for the next coil
- measure UPS lifetime under operating conditions
- IRMIS at JLab
- filled with BNL "training" data
- Preparing for moving into the hall
- permanent VME-based fast DAQ
- Mantis Task Tracker
- role in Hall D Online/Controls effort