GlueX Target Design Mtg, April 21, 2014

From GlueXWiki
Jump to: navigation, search

Present: Chris Keith, Dave Meekins, Josh Pierce, James Brock, Matt Marchlik, Dave Butler, Alexandre Deur, Tim Whitlatch

Minutes from last mtg https://halldweb.jlab.org/wiki/index.php/GlueX_Target_Design_Mtg,_Mar_26,_2014

Agenda

  • Where are we now? Media:Target labor.pdf
  • Cryo hardware status
  • Gas system status
    • Exhaust from pressure relief
    • Plumbing on cart
    • pressure system documentation
    • Storage tanks
  • 3D model/drawings Media:Target assy.pdf
  • Target/Start counter interface
  • Vacuum system update
    • Flange config
  • Controls status
    • updated P&I
    • changes for subcooled config
  • Installation cart update Media:Target cart.jpg
    • Tank config
    • Lifting
    • Controls/panel config
    • Alignment features
  • Scattering chamber status
  • Cell Fabrication Status
    • thermometry
    • Spare cell
  • Schedule
    • Readiness review
    • Assy/test in EEL
    • Install/test in Hall

Info


Minutes

  • James fabricating new cell with straight torlon base and aluminized Kapton(plus a spare) - parts due in this week
  • Target group fabricating an interlock box to hard wire turn off the compressor - Dave Griffith
  • Ok to put kill button in counting room for Target
  • (2) 55 gallon Tanks are in
  • Target group will procure one additional relief valve - 1 relief on each tank and 2 on gas panel
  • Vent stack materials defined and on order - Hall D to assemble
  • Joe Beaufeit to verify compressor power and ensure it is supplied in Hall D
  • May 8th safety review - Tim to send proposal to Patrizia for agenda and pre-brief
  • 5mil kapton window between target and upstream beamline is acceptable
  • 4" gate valve (on order) and turbo for pumping on vacuum chamber and 1.5" valve on beamline (both in house) supplied by Hall D
  • Target group will supply a diaphragm switch hard wired to turn turbo off
  • Tim/Mark to meet with Fernando to determine start counter cabling/patch panel config.
  • Vacuum chamber bottom flange to include 4" pump port and 4 - 2 3/4" conflat ports on order (Matt to check with Dave Meekins if class C ok)
  • Chris sent email to Javier outlining responsibilities
  • Hall D will deliver assembled cart to target group this week. It will have mounts for tanks but the target adjustment cartridges will not be available until next week
  • Tim will get with Jim Dahlberg for more detail on fiducial points.
  • Hall D to supply cooling water for compressor and temp sensors, target group to supply return flow instrumentation. Need to set turn off temps for compressor
  • Need to look at required spares some day - Chris working
  • Target group will buy vacuum instrumentation
  • need to move 4" gate valve downstream and add tee for vacuum instrumentation
  • James pointed out that a cover for the scattering chamber will be needed when removed from position
  • Werth from the detector group is helping Dave B. with the controls
  • Need to control start/stop of compressor (Werth to look at Labview setup)
  • there will be a 20' long flexible gas line from the target to the vent line
  • Chris to supply list of signal names to Dave by the end of the week.
  • Discussion on location of controls crate and magnetic field magnitude - Tim to develop location vs. mag field layouts to help make the decision on the final location for the controls.
  • Need to fit check Start counter hub to target hub next week to ensure proper mating

Action Items