  • Preparation of parts for ECAL -- Sasha
    • - HV long cable: Sammy and Mindy have to assemble 10 cables
    • - HV distribution boards [1][2]
    • - Fix front panel of two LV distribution boards, re-install the boards on the detector frame [3]
    • - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
    • Report from students [4]
    • Installation of HV cables [5][6]
- two remaining bundle of cables will be ready in about a week
  • Students -- Sasha
    • - Expect one student from Wuhan, paperwork is in process.
  • Beam tests with the PS
      • measure shower beam profile and reconstruction in the crystal/LG transition region
      • (install prototype with 5x5 PbWO4 modules + ? LG)
  • Other hardware projects
    • prototype of the ECAL veto counter (?)
  • Analysis/Simulation

Minutes

Attendees: Igal, Laveen, Sasha, Hakob, Stjepan, Phil, Olga, Susan, Jane, S.T.

  • Still missing 6 HV cables
  • Have 2 HV distribution boards, one with 6x8 and one with 12x4 configuration
  • PMT divider installation continues, now finished top 10 layers
    • Check signals with LMS: found a few problems with solder joints, small amplitudes, bad lemo connectors, ...
  • Have prototype (final?) design for LMS driver board to be installed on integrating sphere
  • Igal gave an update on η→π0γγ selection criteria
    • Tested on spring 2017 GlueX data
    • No signal seen
    • Apparent η→3π0 cross section ~2x larger than expected from Jon's studies -- additional background?
    • Machine learning suppresses 3π0 background