JEF meeting, January 10, 2025

From GlueXWiki
Jump to: navigation, search

Connection

Meeting time and location:


Agenda

Preparation of parts for ECAL -- Sasha

-New PCB and parts for the LMS light source arrived to the lab. The LMS board will be assembled and tested during next week.
-Consider to install two more temperature sensors (will try to fix the old ones first), a few sensors have been ordered

-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Implementing ECAL into the GlueX DAQ [1]
- Initial version of the VTP firmware ready. Started testing using a setup with one VTP during the holiday break (some progress has been made)
- VTPs installed on all ECAL VXS crates [2]
- Use new version of DAQ, VTP included as a DAQ component. Will be updated on the entire detector after the ECAL commissioning
-Replace one HV module (problems with the interlock) [8]
  • Update signal translation table [9]
  • Update mapping of the ECAL high voltages and spare HV cables [10]
  • Implement ECAL HV interlock based on the newly installed temperature sensors in the divider region
  • Toook cosmic data with the entire detector powered [11][12]
  • Temperature of the ECAL modules [13][14] [15][16]
Previous temperature scan in the ECAL divider region [17][18][19] [20][21]
  • Safety documents and preparing for the run
Page for shift Takers
ECAL in the Experimental Safety Assessment Document (ESAD)
EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)

ECAL commissioning -- Sasha, All

Calibrations

  • Gain calibration [22]
  • Low-level timing
  • Timing with respect to other detectors

Analysis/Simulation


Minutes

Attendees: Xiaolin, Bill, Axel, Sasha, Zhikun, Igal, Zisis, Tim W., Drew, Liping, Olga, Phil, S.T.

  • Upgrade of LMS light source to use 25 LEDs underway
    • PCB arrived, needs to be populated
      • Assemble and test week of January 13
    • Driver has been updated
  • New temperature sensors have been ordered
  • All VTPs (replacing CTPs for 7 crates) have been installed
    • New VTP firmware now implemented, tested energy summation for 1 VTP
    • Integration into full DAQ system underway
  • Cables for reference PMTs for LMS installed
  • All HV distribution boards installed, cabling complete
    • Several issues found (holes too small, connectors missing locking clip, etc.), these have been addressed
    • One HV channel could not hold desired voltage, use spare connector
    • One HV module had interlock problem, now fixed
    • Signal translation table updated
    • Whole detector checked using scaler rates produced by LMS
    • Ran cosmic ray data over winter break
    • Ran HV scan
  • Temperature sensors installed in upper corners of insert
  • 2 additional fans have been installed
    • Fans in center region are weaker than the new ones
    • Would like to add fans to interlock system
  • Temperature profile for lead glass region shows hot spots
  • Temperature on face of lead tungstate modules rises to 30C after HV(=1.04 kV on all) on for a while
    • Is heat being propagated through the pipe? Sasha blocked the aperture and saw no difference
    • Is head being propagated through the pipe material? Working on concept for cooling the pipe down
    • Is heat begin propagated through the lead tungstate modules themselves? Seems likely.
      • Gradient in z through the module is an issue due to the dependence of light output on temperature, likely to cause distortion of shower profile
    • Relaxation time and time to stabilize after toggling HV is on the scale of hours
    • Cooling power not sufficient: increase fan power? Lower chiller temperature?
  • Zhikun looked at recent cosmic data, saw some nice tracks
    • Fitted amplitude distributions using Landau distribution convoluted with Gaussian, use to estimate new voltage settings