JEF meeting, July 14, 2023

From GlueXWiki
Jump to: navigation, search

Meeting time and location:


Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Spare crystals
    • Received all long signal cables from the first order (1200). Received 450 short signal cables [2]
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers (August/September)
  • Module fabrication -- Sasha
    • All modules have been fabricated, proceed with the final inventorization (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [3] - done
    • Prepare to move modules into Hall D [4] [5][6]
    • Tested, labeled, and bundled (53 bundlesout of 100) [7] of signal cables connected from the flash ADC to the patch panel [8]. Receive printer cartridges, will resume labeling and cable bundling today.
    • Removing signal cables from the FCAL and rearranging signal cables in the hall [9] Rearranging_FCAL_cables - done
      - 400 signal cables were removed,re-labeled and bundled
      - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
      - install two flash ADCs
    • Cutting optical fibers and gluing plastic caps [10]
    • Report from students
    • Test fabricated modules using LMS [11]
  • Testing of PMT dividers -- Sasha / Vlad
    • All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak
  • Simulations/Analysis

Minutes

Attendees: Sasha, Igal, Arshak, Zisis, Olga, Liping, Jane, Jon, Susan, S.T.

  • Jane's group went to Shanghai and inspected 88 SICCAS crystals
    • Found many poor quality crystals (several discolored, several with chips beyond surface level/chamfers)
    • Will reject 23-25
    • Will use remaining as spares or for other projects (not enough to instrument any more columns in insert)
  • Long cables are arriving: have 1200 + 400 from FCAL
    • 53/100 bundles have been prepared
  • Remaining fibers for LMS still not expected until August/September
  • All modules needed for insert have been fabricated, being prepared to move to hall D
    • Testing each one using dark box (looking at waveforms on oscilloscope)
  • Expect first article PMT dividers from outside company soon
  • Stacking of lead glass modules in new frame has started, as of meeting 340 in place
    • Up to layer 10, insert starts after layer 19, maybe middle of week of 7/17/23?
    • Survey&alignment to check levelness before we get too far
  • Arshak polishing fibers
  • Liping visited Modern Physics Institute in China
    • They are working on new accelerator facility to come online in 2025
    • They plan to work on η physics, similar to REDTOP