JEF meeting, September 1, 2023

From GlueXWiki
Jump to: navigation, search

Meeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received 70 crystals from SICCAS. Visual inspection: 4 dim crystals, 8 with many chips (consider to send them back to SICCAS) [1][2]
      - Plan to send back about 10 crystals
    • Received 1100 short signal cables [3]
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers. PR department prepared PO but forgot to send it out
  • Module fabrication -- Sasha
    • All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [4] - done
    • All crystals moved to Hall D[5] [6][7] - done
    • Tested, labeled, and bundled all 100 (+ 2 spares) [8] signal cables connected from the flash ADC to the patch panel [9] - done
    • Test and label 1100 short signal cables - ongoing
    • Tested fabricated modules using LMS [10] - done (need to update the wiki page)
    • Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
    • Work on refurbishing LG modules rejected during installation
      - Fixed about 120 modules with different small issues: soldering compound bumps on the brass assembly, small bubbles on silicon cookies, small issues with wrapping
      - Mindy is working on re-wrapping of about 30 crystals. She also continues soldering wires to the PMT connectors
    • Report from students
  • Testing of PMT dividers -- Sasha / Vlad
    • -Continue with testing dividers, should be done during this/next week
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak
  • Discussion of the budget request for 2024 -- Sasha (all)
  • Miscellaneous
- Profiler to measure shower shape
- Veto in the insert region

Minutes

Attendees: Liping, Bill, Phil, Zisis, Igal, Jon, Sasha, Jane, Olga, S.T.

  • 10 new SICCAS crystals were sufficiently bad that we are likely to send them back
  • Discovered that PO for remaining set of fibers for LMS was never sent out! Now fixed, asked company to expedite the order.
  • Installation of FCAL-2 continues
    • Reject ~120 modules with issues (bumps from soldering, bubbles from cookies, wrinkles in wrapping,...), will be redone
    • 33 ECAL layers installed + 1 more lead glass layer, needed shims to make surface flat
  • PMT divider tests ongong, will give green light to company soon
  • Budget requests
    • 7.5 months of students
    • Scintillating fiber profiler (for measuring shower shape)
    • Scinillator detector for "inner TOF"/veto -- prototype