Run Planning Meeting Notes, September 8 - September 14, 2022

From GlueXWiki
Jump to: navigation, search

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook

Back to Run Coordination Meetings:Fall2022

Wednesday, September 14

Past 24 Hours

Issues

Beam position shifts on 5C11 YPOS

Plan

  • Maintenance day today
    • FCAL Base replacement (Malte)
    • Installation of setup in PS for GEM-TRD
    • Beam restoration expected around 8:00PM
  • Fill LHe target
  • Take production data at 200nA

Tuesday, September 13

Past 24 Hours

Issues

Plan

  • Empty Target running
  • Maintenance day tomorrow
    • Beam off around 6:30AM, restored during swing shift (~8PM)

Monday, September 12

Over the Weekend

Issues

  • FCAL Bases:
    • Had to reset a few bases throughout the weekend using standard procedure. One base (35,5) was not responding to power-reset and Malte will investigate next access.
    • Another base not holding HV and needs to be replaced next access
  • CDC AI turned off per Naomi's request.

Plan

  • Empty Target, take TAC Run
  • Continue taking empty-target data until Maintenance day on Wednesday

Friday, September 9

Past 24 hours

Issues

Plan

  • Continue taking production data at 200nA.
    • Production runs at small intensity (50nA and 100nA) over the weekend?
  • PrimEx Run Plan

Thursday, September 8

Past 24 hours

Issues

Plan