Revision as of 08:44, 16 September 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Crystals.
- 45 CRYTUR crystals received from Physics division
- currently available/ordered + CCAL: 1593 + (9) + 20 (recent order) = 1622 (may need to order more spares (?) )
- Wrapped CRYTUR crystals: 687
- - Available for wrapping: 722 - 687 = 35
- - DSG group continues wrapping
- Preparation of parts
- Crystals.
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 1206 (a new milestone)
- All SICCAS 576 SICCAS
- 630 CRYTUR, Remaining: 52
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak