Difference between revisions of "Feb 12, 2009 Calorimetry"
From GlueXWiki
(→Tentative Agenda) |
(→Tentative Agenda) |
||
Line 30: | Line 30: | ||
## [Performance of SiPMs below room temperature] | ## [Performance of SiPMs below room temperature] | ||
## [[Energy threshold for various assumed PDE and DR combinations]] | ## [[Energy threshold for various assumed PDE and DR combinations]] | ||
− | # Simulations (Blake et al) | + | # Simulations (Blake et al): a report is expected at the next meeting (Feb 26) |
− | ## | + | ## See [[Physics Working Group Meetings]] for discussions to this point. |
# Any other business | # Any other business | ||
=Minutes= | =Minutes= |
Revision as of 18:44, 11 February 2009
Teleconference Time: 11:00 EST/10:00 CST
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 39527048# (remember the "#")
Contents
Items for followup from Jan 15 meeting
- Resolution studies (Blake)
- Develop criteria for evaluating resolution studies
- Study impact of inactive material at the end of Bcal on acceptance.
- Check what configuration (thresholds, step sizes, stack? parameters for secondaries, etc) is being used for the Hall D simulations (Regina)
- Writeup fiber handling procedures for review by Kuraray (UofR - draft given to JLab)
- Lead contract completion including lead sizes (Tim - RFI out this week, RFQ out next week)
Documents to Review
Tentative Agenda
- Announcements
- FCAL Update
- BCAL Update
- Bcal construction schedule (Regina)
- BCAL Readout
- Roadmap toward a decision for Bcal Readout
- [Performance of SiPMs below room temperature]
- Energy threshold for various assumed PDE and DR combinations
- Simulations (Blake et al): a report is expected at the next meeting (Feb 26)
- See Physics Working Group Meetings for discussions to this point.
- Any other business