(Created page with "eeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection informa...") |
(→Agenda) |
||
Line 6: | Line 6: | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
+ | ** - signal cables - done | ||
+ | ** - signal patch [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done | ||
+ | ** - HV cables: received 165 short cables during this week | ||
+ | ** - HV distribution boards: in preparation | ||
+ | ** - LV cables: received first article, started production (Dec. 7), expect the | ||
+ | ** - LV distribution boards. The LV distribution boards have been ordered. | ||
+ | ** - Optical fibers: received all | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
+ | ** - Testing and labeling cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ] | ||
+ | ** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ] | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals] - done | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] - done | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg Prepared 26 modules for TAC and 35 modules for beam tests] - done | ||
+ | ** - Preparation of the LMS | ||
+ | *** - All fibers are ready for the installation. The plate was machined and polised [https://logbooks.jlab.org/entry/4228633] | ||
+ | *** - Installing light tight covers on the plastic caps [https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt4.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt3.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt1.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt2.jpg] | ||
+ | *** - Meeting with Fernando and Chris regarding LED drivers | ||
+ | ** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests] | ||
+ | ** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran | ||
− | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad | + | ** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] |
+ | ** - Tested 420 dividers [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers] | ||
+ | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | ||
+ | ** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey] | ||
+ | *** - waiting for survey results | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] | ||
+ | ** Meeting with Chris Cuevas regarding installing optical fibers and patch panels | ||
+ | ** Installation of electronics [https://halldweb.jlab.org/wiki/index.php/FCAL2_Crates] | ||
+ | |||
* '''[[Lead Glass Efforts]]''' -- Malte / Mark / Kevin / Zisis | * '''[[Lead Glass Efforts]]''' -- Malte / Mark / Kevin / Zisis | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' |
Revision as of 17:05, 14 December 2023
eeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch [1] - done
- - HV cables: received 165 short cables during this week
- - HV distribution boards: in preparation
- - LV cables: received first article, started production (Dec. 7), expect the
- - LV distribution boards. The LV distribution boards have been ordered.
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- - Testing and labeling cables (Recently labeled cables in boxes)[2]
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
- Wrapped crystals - done
- Parts for TAC[4] - done
- Prepared 26 modules for TAC and 35 modules for beam tests - done
- - Preparation of the LMS
- - Radiation tests of the PMT active base [10]
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [13][14][15]
- Detector survey
- - waiting for survey results
- Detector installation page
- Updates from the meetings with Tim's group [16]
- Meeting with Chris Cuevas regarding installing optical fibers and patch panels
- Installation of electronics [17]
- Lead Glass Efforts -- Malte / Mark / Kevin / Zisis
- Analysis/Simulation