Line 12: Line 12:
 
:: Expected delivery date of the ECAL HV distribution boards 11/18/2024 [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
 
:: Expected delivery date of the ECAL HV distribution boards 11/18/2024 [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
 
:: Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered
 
:: Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered
 +
:: Four temperature sensors (RTD) were ordered. They will be installed in the ECAL divider region
 +
:: Tim ordered two additional fans to increase the air flow in the divider region
 
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All  
 
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All  
 
* Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928]
 
* Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928]

Revision as of 19:12, 24 November 2024

Connection

Meeting time and location:


Agenda

Preparation of parts for ECAL -- Sasha

Expected delivery date of the ECAL HV distribution boards 11/18/2024 [1][2]
Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered
Four temperature sensors (RTD) were ordered. They will be installed in the ECAL divider region
Tim ordered two additional fans to increase the air flow in the divider region

Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Implementing ECAL into the GlueX DAQ [3]
- rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- implementing flash ADC scalers [6][7]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- implementing and verifying ECAL LMS trigger [9]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- New version of DAQ, VTP included as a DAQ component [11]
Meeting with Tim, additional fans will be installed
  • Repairing a few ECAL LMS optical fibers [27][28]
  • Preparing for the installation of the insulation on the detector face
- Removing Tedlar from the face of the detector [29]
- ECAL flash ADC scalers before removing detector face cover [30]
  • Preparing for the run
Page for shift Takers
ECAL in the Experimental Safety Assessment Document (ESAD)
EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- Installing additional fans
- Installing insulation on the detector's face

Restoring PS test setup [31]

ECAL commissioning -- Sasha, All

Laveen update[[32]]

Calibrations

-First look on cosmic data -- Zhikun

Analysis/Simulation