Difference between revisions of "JEF meeting, November 22, 2024"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 10: Line 10:
 
'''Preparation of parts for ECAL''' -- Sasha  
 
'''Preparation of parts for ECAL''' -- Sasha  
  
:: Expected delivery date of the ECAL HV distribution boards 11/18/2024 [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
+
:: -Expected delivery date of the ECAL HV distribution boards 11/18/2024 [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
:: Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered
+
:: -Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered
:: Four temperature sensors (RTD) were ordered. They will be installed in the ECAL divider region
+
:: -Four temperature sensors (RTD) were ordered. They will be installed in the ECAL divider region
:: Tim ordered two additional fans to increase the air flow in the divider region
+
:: -Tim ordered two additional fans to increase the air flow in the divider region
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All  
+
'''-Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All  
 
* Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928]
 
* Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928]
 
:: - rocecal3 crate was fixed [https://logbooks.jlab.org/entry/4317415] (initial DAQ implementation [https://logbooks.jlab.org/entry/4316928])
 
:: - rocecal3 crate was fixed [https://logbooks.jlab.org/entry/4317415] (initial DAQ implementation [https://logbooks.jlab.org/entry/4316928])

Revision as of 19:12, 24 November 2024

Connection

Meeting time and location:


Agenda

Preparation of parts for ECAL -- Sasha

-Expected delivery date of the ECAL HV distribution boards 11/18/2024 [1][2]
-Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered
-Four temperature sensors (RTD) were ordered. They will be installed in the ECAL divider region
-Tim ordered two additional fans to increase the air flow in the divider region

-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Implementing ECAL into the GlueX DAQ [3]
- rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- implementing flash ADC scalers [6][7]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- implementing and verifying ECAL LMS trigger [9]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- New version of DAQ, VTP included as a DAQ component [11]
Meeting with Tim, additional fans will be installed
  • Repairing a few ECAL LMS optical fibers [27][28]
  • Preparing for the installation of the insulation on the detector face
- Removing Tedlar from the face of the detector [29]
- ECAL flash ADC scalers before removing detector face cover [30]
  • Preparing for the run
Page for shift Takers
ECAL in the Experimental Safety Assessment Document (ESAD)
EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- Installing additional fans
- Installing insulation on the detector's face

Restoring PS test setup [31]

ECAL commissioning -- Sasha, All

Laveen update[[32]]

Calibrations

-First look on cosmic data -- Zhikun

Analysis/Simulation