Difference between revisions of "JEF meeting, November 22, 2024"
From GlueXWiki
(Created page with "= Connection = Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information C...") |
|||
(6 intermediate revisions by one other user not shown) | |||
Line 4: | Line 4: | ||
*9:30 am EST (JLab time) remote only | *9:30 am EST (JLab time) remote only | ||
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information] | * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information] | ||
+ | |||
Line 9: | Line 10: | ||
'''Preparation of parts for ECAL''' -- Sasha | '''Preparation of parts for ECAL''' -- Sasha | ||
− | '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All | + | :: -Expected delivery date of the ECAL HV distribution boards 11/18/2024 [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg] |
+ | :: -Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered | ||
+ | :: -Four temperature sensors (RTD) were ordered. They will be installed in the ECAL divider region | ||
+ | :: -Tim ordered two additional fans to increase the air flow in the divider region | ||
+ | '''-Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All | ||
+ | * Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928] | ||
+ | :: - rocecal3 crate was fixed [https://logbooks.jlab.org/entry/4317415] (initial DAQ implementation [https://logbooks.jlab.org/entry/4316928]) | ||
+ | :: - implementing flash ADC scalers [https://logbooks.jlab.org/entry/4319280][https://logbooks.jlab.org/entry/4319672] | ||
+ | :: - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [https://logbooks.jlab.org/entry/4317904] | ||
+ | :: - implementing and verifying ECAL LMS trigger [https://logbooks.jlab.org/entry/4317903] | ||
+ | :: - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [https://logbooks.jlab.org/entry/4317905] | ||
+ | :: - Start implementing VTP trigger modules. Requires modification of firmware. <span style="color:red"> The trigger crates may be unavailable for 1 - 1.5 months.</span> | ||
+ | ::: - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now | ||
+ | ::: - New version of DAQ, VTP included as a DAQ component [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_08_2024/daq_vtp.png] | ||
+ | * Installation of scintillating paddles for cosmic tests [https://logbooks.jlab.org/entry/4317905] [https://logbooks.jlab.org/entry/4318834][https://logbooks.jlab.org/entry/4319535] | ||
+ | * ECAL HV interlock check [https://logbooks.jlab.org/entry/4318704] | ||
+ | * Cable map of the ECAL LG modules after installing ECAL [https://logbooks.jlab.org/entry/4318588] | ||
+ | * Reinstalling cables on the ECAL LV distribution board [https://logbooks.jlab.org/entry/4318905] | ||
+ | * [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha | ||
+ | * [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | * Commissioning north part of the ECAL (instrumented with 2 temporary HV distribution boards) [https://logbooks.jlab.org/entry/4319280][https://logbooks.jlab.org/entry/4319672][https://logbooks.jlab.org/entry/4320378][https://logbooks.jlab.org/entry/4320977] | ||
+ | * First cosmic event in the ECAL [https://logbooks.jlab.org/entry/4320980] | ||
+ | * Temperature scan in the ECAL divider region [https://logbooks.jlab.org/entry/4320981][https://logbooks.jlab.org/entry/4321406][https://logbooks.jlab.org/entry/4321241][https://logbooks.jlab.org/entry/4321188] | ||
+ | :: Meeting with Tim, additional fans will be installed | ||
+ | * Repairing a few ECAL LMS optical fibers [https://logbooks.jlab.org/entry/4320978][https://logbooks.jlab.org/entry/4321408] | ||
+ | * Preparing for the installation of the insulation on the detector face | ||
+ | :: - Removing Tedlar from the face of the detector [https://logbooks.jlab.org/entry/4321573] | ||
+ | :: - ECAL flash ADC scalers before removing detector face cover [https://logbooks.jlab.org/entry/4321569] | ||
+ | * Preparing for the run | ||
+ | :: [https://halldweb.jlab.org/hdops/wiki/index.php/Electromagnetic_Calorimeter Page for shift Takers ] | ||
+ | :: [https://halldweb.jlab.org/detectors/fcal2/esad_safety ECAL in the Experimental Safety Assessment Document (ESAD)] | ||
+ | :: EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236) | ||
+ | * [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings] | ||
+ | * Remaining installation tasks | ||
+ | :: - Installing additional fans | ||
+ | :: - Installing insulation on the detector's face | ||
'''Restoring PS test setup''' [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/ps_setup.jpg] | '''Restoring PS test setup''' [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/ps_setup.jpg] | ||
''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ||
+ | |||
+ | '''Laveen update'''[[https://halldweb.jlab.org/DocDB/0066/006689/001/Nov15-Update.pdf]] | ||
'''Calibrations''' | '''Calibrations''' | ||
+ | |||
+ | ::-[https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_15_2024/2024.11.8-2024.11.14.pdf First look on cosmic data -- Zhikun] | ||
'''Analysis/Simulation''' | '''Analysis/Simulation''' | ||
+ | |||
+ | =Minutes= | ||
+ | Attendees: Sasha, Zhikun, Phil, Bill, Vlad, Jane, Olga, Laveen, Liping, Xiaolin, S.T. | ||
+ | * Final inspection of optical fibers completed, techs put new Tedlar on FCAL face and will install new insulation foam | ||
+ | * Everything looks good on the ECAL north side according to scalers | ||
+ | * Still waiting for HV boxes | ||
+ | * Tests continue to increase LMS light output | ||
+ | ** Fernando found brighter LEDs, will test | ||
+ | ** Driver modified, added many more LEDS to board (5 -> 25) | ||
+ | ** Will still use integrating sphere | ||
+ | * Four more temperature sensors for ECAL divider region ordered | ||
+ | * Two more fans ordered, to be place to left and right of existing assembly | ||
+ | * Laveen working on reference PMT design | ||
+ | * One LV channel needs to be fixed | ||
+ | * Documentation coming together: ECAL shift page for upcoming run, ECAL in ESAD, ePAS for general maintenance | ||
+ | * Zhikun developed script to create new HV config file based on Amp<->HV curve | ||
+ | ** Will use fitted peak positions from cosmic data | ||
+ | * CSS for HV control ready to be tested | ||
+ | * Calibration plans to be discussed next meeting | ||
+ | ** Cosmics for initial HV settings | ||
+ | ** Compton events | ||
+ | ** π0 refinement |
Latest revision as of 09:40, 25 November 2024
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- -Expected delivery date of the ECAL HV distribution boards 11/18/2024 [1][2]
- -Meeting with Fernando and Chris regarding updating the LMS light source, a few new LEDs have been ordered
- -Four temperature sensors (RTD) were ordered. They will be installed in the ECAL divider region
- -Tim ordered two additional fans to increase the air flow in the divider region
-Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Implementing ECAL into the GlueX DAQ [3]
- - rocecal3 crate was fixed [4] (initial DAQ implementation [5])
- - implementing flash ADC scalers [6][7]
- - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- - implementing and verifying ECAL LMS trigger [9]
- - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- - Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- - New version of DAQ, VTP included as a DAQ component [11]
- Installation of scintillating paddles for cosmic tests [12] [13][14]
- ECAL HV interlock check [15]
- Cable map of the ECAL LG modules after installing ECAL [16]
- Reinstalling cables on the ECAL LV distribution board [17]
- Safety briefings - Vlad, Sasha
- Detector installation page
- Commissioning north part of the ECAL (instrumented with 2 temporary HV distribution boards) [18][19][20][21]
- First cosmic event in the ECAL [22]
- Temperature scan in the ECAL divider region [23][24][25][26]
- Meeting with Tim, additional fans will be installed
- Repairing a few ECAL LMS optical fibers [27][28]
- Preparing for the installation of the insulation on the detector face
- Preparing for the run
- Page for shift Takers
- ECAL in the Experimental Safety Assessment Document (ESAD)
- EPAS for Maintenance of the Hall D ECAL (Jlab-PTW-5236)
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Installing additional fans
- - Installing insulation on the detector's face
Restoring PS test setup [31]
ECAL commissioning -- Sasha, All
Laveen update[[32]]
Calibrations
Analysis/Simulation
Minutes
Attendees: Sasha, Zhikun, Phil, Bill, Vlad, Jane, Olga, Laveen, Liping, Xiaolin, S.T.
- Final inspection of optical fibers completed, techs put new Tedlar on FCAL face and will install new insulation foam
- Everything looks good on the ECAL north side according to scalers
- Still waiting for HV boxes
- Tests continue to increase LMS light output
- Fernando found brighter LEDs, will test
- Driver modified, added many more LEDS to board (5 -> 25)
- Will still use integrating sphere
- Four more temperature sensors for ECAL divider region ordered
- Two more fans ordered, to be place to left and right of existing assembly
- Laveen working on reference PMT design
- One LV channel needs to be fixed
- Documentation coming together: ECAL shift page for upcoming run, ECAL in ESAD, ePAS for general maintenance
- Zhikun developed script to create new HV config file based on Amp<->HV curve
- Will use fitted peak positions from cosmic data
- CSS for HV control ready to be tested
- Calibration plans to be discussed next meeting
- Cosmics for initial HV settings
- Compton events
- π0 refinement