Line 10: | Line 10: | ||
** Crystals: | ** Crystals: | ||
**: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> | **: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> | ||
− | **: - | + | **: - 70 SICCAS crystals were shipped to us |
− | ** Received | + | ** Received 600 short signal cables [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/short_signal.jpg], ready to label |
** Procurement parts for the LMS: | ** Procurement parts for the LMS: | ||
**: - Waiting for 7,600 ft of optical fibers (August/September) | **: - Waiting for 7,600 ft of optical fibers (August/September) | ||
* '''Module fabrication''' -- Sasha | * '''Module fabrication''' -- Sasha | ||
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | ||
− | ** All modules have been fabricated, | + | ** All modules have been fabricated, checked, and inventorized (about 1610 modules in total) |
− | ** | + | ** Finished with fixin about 20 modules with small imperfections (overlapping Tedlar) |
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done | ** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done | ||
− | ** Prepare to move modules into Hall D [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move.jpg] [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move2.jpg] | + | ** Prepare to move modules into Hall D [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move.jpg] [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move2.jpg], wrap modules with sort towels. |
− | ** Prepare space for the ECAL in Hall D. | + | ** Prepare space for the ECAL modules (shelves, etc.) in Hall D. Moved 134 CRYTUR and 475 SICCAS crystals (609 in total to Hall D) [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move3.jpg]. |
− | ** Tested, labeled, and bundled ( | + | ** Tested, labeled, and bundled (86 bundles out of 100) [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/signal_bundles.jpg] signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]. Receive cartridges for the printer, will resume labeling and cable bundling today. |
** Removing signal cables from the FCAL and rearranging signal cables in the hall [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] [https://halldweb.jlab.org/wiki/index.php/Rearranging_FCAL_cables Rearranging_FCAL_cables] - done | ** Removing signal cables from the FCAL and rearranging signal cables in the hall [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] [https://halldweb.jlab.org/wiki/index.php/Rearranging_FCAL_cables Rearranging_FCAL_cables] - done | ||
**: - 400 signal cables were removed,re-labeled and bundled | **: - 400 signal cables were removed,re-labeled and bundled | ||
**: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL) | **: - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL) | ||
**: - install two flash ADCs | **: - install two flash ADCs | ||
− | ** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg] | + | ** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg], waiting for 7600 ft of optical fibers |
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ||
** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules] 644 modules have been tested. | ** Test fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules] 644 modules have been tested. |
Revision as of 09:10, 28 July 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Module fabrication -- Sasha
- All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
- Finished with fixin about 20 modules with small imperfections (overlapping Tedlar)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [3] - done
- Prepare to move modules into Hall D [4] [5][6], wrap modules with sort towels.
- Prepare space for the ECAL modules (shelves, etc.) in Hall D. Moved 134 CRYTUR and 475 SICCAS crystals (609 in total to Hall D) [7].
- Tested, labeled, and bundled (86 bundles out of 100) [8] signal cables connected from the flash ADC to the patch panel [9]. Receive cartridges for the printer, will resume labeling and cable bundling today.
- Removing signal cables from the FCAL and rearranging signal cables in the hall [10] Rearranging_FCAL_cables - done
- - 400 signal cables were removed,re-labeled and bundled
- - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
- - install two flash ADCs
- Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
- Report from students
- Test fabricated modules using LMS [12] 644 modules have been tested.
- Testing of PMT dividers -- Sasha / Vlad
- All electronics components received, will be shiped to the company to fabricate dividers today (Chris)
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Started installing detector modules [13][14][15]
- Detector installation page
- Updates from the meetings with Tim's group [16]
- Discussion of the FCAL2 installation procedures [17]
- Final mapping of low-voltage cables
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak