=Agenda= | =Agenda= | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
− | ** - signal cables: | + | ** - signal cables: all cables are ready. 240 have been labeled during this week. |
** - signal patch panels are ready [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] | ** - signal patch panels are ready [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] | ||
** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production | ** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production | ||
− | ** - HV distribution boards: | + | ** - HV distribution boards: check HV distribution boards during this week. Chris is finalizing design of the distribution board, should order 4 boards soon. |
** - LV cables: ordered, lead time unclear | ** - LV cables: ordered, lead time unclear | ||
− | ** - LV distribution boards: | + | ** - LV distribution boards: met with Chris and Stephanie on Monday last week. The design of the LV distribution board has been fixed. |
** - Optical fibers: received all | ** - Optical fibers: received all | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
− | ** Tested and labeled ~ | + | ** Tested and labeled ~240 short signal cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)] |
− | ** Final inspection of installed lead glass and lead tungstate modules [https://logbooks. | + | ** Final inspection of installed lead glass and lead tungstate modules [https://logbooks.jl |
− | + | ||
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
− | ** | + | ** Prepare modules for the TAC and prototypes (many of them are low quality) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ] |
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad |
Revision as of 08:49, 20 October 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: all cables are ready. 240 have been labeled during this week.
- - signal patch panels are ready [1]
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: check HV distribution boards during this week. Chris is finalizing design of the distribution board, should order 4 boards soon.
- - LV cables: ordered, lead time unclear
- - LV distribution boards: met with Chris and Stephanie on Monday last week. The design of the LV distribution board has been fixed.
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- Tested and labeled ~240 short signal cables (Recently labeled cables in boxes)
- Final inspection of installed lead glass and lead tungstate modules [https://logbooks.jl
- Summer Students (2023)
- Prepare modules for the TAC and prototypes (many of them are low quality) [2]
- Testing of PMT dividers -- Sasha / Vlad
- - Test setup is ready. About 30 dividers are ready for testing
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- Plastic caps have been glued to all fibers
- Returning low-quality crystals to SICCAS -- Sasha
- 11 crystals were wrapped and placed into the box; they are ready for shipment to SICCAS [8]
- Analysis/Simulation
- First look at impact of GEMTRD -- Simon