Difference between revisions of "JEF meeting, February 16, 2024"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 32: | Line 32: | ||
** Installation of the LMS | ** Installation of the LMS | ||
*** 175 fibers installed during this week (488 in total) [https://logbooks.jlab.org/entry/4253130] [https://logbooks.jlab.org/entry/4249236] | *** 175 fibers installed during this week (488 in total) [https://logbooks.jlab.org/entry/4253130] [https://logbooks.jlab.org/entry/4249236] | ||
− | ** Cable and divider installation [https://logbooks.jlab.org/entry/4249243][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable1.jpg][https://halldweb.jlab.org/ | + | ** Cable and divider installation [https://logbooks.jlab.org/entry/4249243][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable1.jpg] |
+ | [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable2.jpg] | ||
** Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ) | ** Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ) | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' | ||
** [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6347 Rough draft of Feb. collaboration talk] -- Simon | ** [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6347 Rough draft of Feb. collaboration talk] -- Simon |
Revision as of 10:19, 16 February 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 165 cables 1445 in total
- - HV distribution boards: in preparation
- - LV cables: 100 cables received, 250 cables in total
- - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
- - Optical fibers and parts for the trigger/DAQ have been ordered
- Ongoing projects -- Sasha, all
- - Testing and labeling cables, 100 short LV cables tested and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Radiation tests of the PMT active base [5]
- Finished tests, working on the tech note
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / George
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
- Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
- Detector installation page
- Analysis/Simulation