Difference between revisions of "JEF meeting, October 4, 2024"

From GlueXWiki
Jump to: navigation, search
Line 11: Line 11:
 
::  - Sent out request of quotes for HV boards
 
::  - Sent out request of quotes for HV boards
 
* - Two panels for the LV distribution boards received, need to re-connect cables (Sasha, Laveen, Vlad) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg]
 
* - Two panels for the LV distribution boards received, need to re-connect cables (Sasha, Laveen, Vlad) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg]
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen
+
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All
 
* Installation and testing dividers has been completed [https://logbooks.jlab.org/entry/4316213]
 
* Installation and testing dividers has been completed [https://logbooks.jlab.org/entry/4316213]
 
:: - need to arrange cables on chains  - done
 
:: - need to arrange cables on chains  - done

Revision as of 09:13, 4 October 2024

Meeting time and location:


Preparation of parts for ECAL -- Sasha

  • - long HV cables - done
  • - HV distribution boards [1][2]
- 5 (12 x 4) and 5 (6 x 8) boards have been received. Received all PCB boards. Soldering wires to connectors
- Sent out request of quotes for HV boards
  • - Two panels for the LV distribution boards received, need to re-connect cables (Sasha, Laveen, Vlad) [3]

Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Installation and testing dividers has been completed [4]
- need to arrange cables on chains - done
- need to arrange cables on cable trays - done [5]
- preparing spare cables (7 short HV, 8 signal and LV) -done
  • Installation of the light distribution board of the ECAL LMS [6]
  • Implementing ECAL into the GlueX DAQ [7]
- rocecal3 crate is working now [8] (initial DAQ implementation [9])
- implementing flash ADC scalers [10]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done
- Connecting cooling pipes to the ECAL fan (done by tech group)
- Installing dark room ceiling and insulation inside the room, required for cooling test (next week)
- Test cooling system (next week)
- Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)

Students -- Sasha

  • Visit of Zhikun from Wuhan

Restoring PS test setup [11]

ECAL commissioning -- Sasha, All