Difference between revisions of "Photon Beam Commissioning Discussion July 16, 2014"
From GlueXWiki
m (Text replacement - "hdops.jlab.org/wiki" to "halldweb.jlab.org/hdops/wiki") |
|||
Line 10: | Line 10: | ||
== References == | == References == | ||
− | * [https:// | + | * [https://halldweb.jlab.org/hdops/wiki/index.php/Hall_D_Commissioning Hall D Commissioning Pages] |
* [[Media:HallD_beam_delivery_proc_1b9.pdf | DRAFT Accelerator Hall D Beam Delivery Procedures(V.1b9)]] | * [[Media:HallD_beam_delivery_proc_1b9.pdf | DRAFT Accelerator Hall D Beam Delivery Procedures(V.1b9)]] | ||
* [[Media:Tagger_operation_procedure.docx | DRAFT Accelerator Tagger Magnet Operation Procedures(V. 0)]] | * [[Media:Tagger_operation_procedure.docx | DRAFT Accelerator Tagger Magnet Operation Procedures(V. 0)]] |
Latest revision as of 17:22, 31 March 2015
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
- Hall D Commissioning Pages
- DRAFT Accelerator Hall D Beam Delivery Procedures(V.1b9)
- DRAFT Accelerator Tagger Magnet Operation Procedures(V. 0)
- DRAFT Accelerator Hall D Ion Chamber Functional Test Procedure(V.1b3)
- DRAFT Accelerator Hall D Ion Chamber Calibration Procedure(V.1b2)
Action Items
-
Send link to accelerator commissioning procedure (Mike) - Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this
-
Todd will provide the magnetic field of the quadrupole immediately upstream of the tagger magnet (Todd)Todd has requested the information and will pass it on when he gets it -
Check that radiator set for commissioning is available (Alexandre, Hovanes)Material for 2x10^-4 available, Alexandre will order the 1x10^-4 material -
Check that RadCon detectors are available/installed in tagger hall and hall D (Alexandre)Draft plan with Radcon is in place and will be pursued -
Check that 'rapid access system' is being implemented in Hall D (Alexandre)Draft plan with RadCon is in place and will be pursued. -
Organize preparations for review (Elton).See minutes
Agenda
- Announcements
- Electron Commissioning (Todd/Mike)
- Photon Commissioning Draft (Alexandre)
- Radiation monitors
- Aug 8 Review:
- Other business
Minutes
Attending: Elton, Alexandre, Hovanes, Eugene, Sasha (Hall D); Todd, Michael (Accelerator)
- Announcements
- Electron Commissioning (Todd/Mike)
- Procedures were scanned and comments made. Alexandre has read the documents and asked for some clarifications
- Specifically, the plan is general and needs to be adapted to the commissioning. For beam delivery #58 should be changed to active collimator long term. For the commissioning we need to insert a test plan to align the photon beam.
- Specific comments to the procedures can be sent to Michael.
- Photon Commissioning Draft (Alexandre)
- Thickness of radiators discussed and settled
- Plan to use cw for beam delivery with radiator inserted. Goal is to use about 100 nA.
- Alexandre has updated the procedure based on comments from last week and will also adjust based on comments today
- Discussion (unresolved) on how many locations to place the profile monitor: a) in front of collimator [for initial alignment] b) upstream of target [under discussion] c) downstream of Fcal [long term operation]
- Need to update the photon beam commissioning procedure with quantitative rates and ranges of expected tuning parameters, e.g. currents in corrector magnets
- Radiation monitors
- Alexandre is in communication with RadCon to borrow some radiation monitors for the commissioning run.
- neutron, gamma monitors in tagger hall (one at the electronic rack location, one at the microscope location)
- gamma monitor in collimator cave.
- Monitors could be purchased later if we believe they are necessary for long-term use.
- Aug 8 Review: Location CC L102
- Reviewers: Mike Spata, Brian Freeman, Stepan Stepanyan
- Charge/Schedule (Elton/Eugene)
- Materials: Accelerator Procedures (Mike); Plan for photon beam commissioning (Alexandre)
- Talks: Overview/Goals/Charge (Eugene); Photon beam properties (Richard); Electron beam commissioning (Michael); Photon beam commissioning (Alexandre)
- Other business
- Next meeting: Wed Jul 23 4 pm.