Difference between revisions of "JEF meeting, June 24, 2022"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 13: | Line 13: | ||
*** Module fabrication | *** Module fabrication | ||
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals:] 491 (60 + 185 + 166 + 80) | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals:] 491 (60 + 185 + 166 + 80) | ||
− | *** Remaining 126, 1.5 weeks of work) | + | *** Remaining 126, 1.5 weeks of work) |
**Students reports | **Students reports | ||
* Module fabrication -- Sasha | * Module fabrication -- Sasha | ||
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] | ||
− | ** Fabricated modules: <span style="color:#FF0000"> Total 598 </span> | + | ** Fabricated modules: <span style="color:#FF0000"> Total 598 </span> |
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All 561 SICCAS] | ||
+ | *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 37 CRYTUR], Remaining: 590) | ||
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/clean_room.jpg Clean room EEL126] | ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/clean_room.jpg Clean room EEL126] | ||
Revision as of 21:48, 23 June 2022
meeting time and location
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- DNP2022 abstract
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Moving crystals from JLab's pool to the Lab [1][2] Moved 335 CRYTUR crystals (need 550).
- Preparation of parts[3][4][5]
- Preshaping ESR foils
- Wrapping crystals
- Module fabrication
- Wrapped CRYTUR crystals: 491 (60 + 185 + 166 + 80)
- Remaining 126, 1.5 weeks of work)
- Students reports
- Module fabrication -- Sasha
- Status of fabrication
- Fabricated modules: Total 598
- All 561 SICCAS
- 37 CRYTUR, Remaining: 590)
- Clean room EEL126
- Students reports
- Module fabrication -- Sasha
- Light Monitoring System -- Arshak