Difference between revisions of "JEF meeting, September 2, 2022"
From GlueXWiki
(→Agenda) |
|||
Line 8: | Line 8: | ||
* Preparation of parts for FCAL2 modules -- Sasha | * Preparation of parts for FCAL2 modules -- Sasha | ||
− | ** Crystals. [https://halldweb.jlab.org/wiki/index.php/CRYTUR] | + | ** Crystals. [https://halldweb.jlab.org/wiki/index.php/CRYTUR] |
− | *** currently available/ordered + CCAL: 1593 + (9) | + | *** 30 CRYTUR crystals received from Physics division |
+ | *** 20 more CRYTUR crystals have been ordered. | ||
+ | *** currently available/ordered + CCAL: 1593 + (9) + 20 (recent order) = 1622 (may need to order more spares (?) ) | ||
** Meeting with the DSG group: Mindy and George will continue working on the project in September | ** Meeting with the DSG group: Mindy and George will continue working on the project in September | ||
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students1.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students3.jpg]. Remaining components: | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students1.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students3.jpg]. Remaining components: |
Revision as of 11:08, 1 September 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Crystals. [1]
- 30 CRYTUR crystals received from Physics division
- 20 more CRYTUR crystals have been ordered.
- currently available/ordered + CCAL: 1593 + (9) + 20 (recent order) = 1622 (may need to order more spares (?) )
- Meeting with the DSG group: Mindy and George will continue working on the project in September
- Preparation of parts[2][3][4]. Remaining components:
- 300 brass assemblies (Keith and Chris will continue to work on them, waiting for straps)
- 200 light guides, will be delivered during a couple of next weeks.
- 400 PMT housings, expect to receive during next two months (bottleneck now)
- Wrapped CRYTUR crystals: 682
- All currently available
- Crystals. [1]
- Module fabrication -- Sasha
- Received 72 PMT housings from Tim a couple of days ago; used practically all of them
- Status of fabrication
- Fabricated modules: Total 1206 (a new milestone)
- All SICCAS 576 SICCAS
- 630 CRYTUR, Remaining: 52
- Clean room EEL126 [5][6]
- Expect to move to the new lab EEL108 (the same building) [7]
- Work on amending safety docs
- All students will leave during this week (11 students have been working on the project during this summer)
- Great job !
- (had also a chance to work on the CCAL project [8])
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak