Difference between revisions of "JEF meeting, March 15, 2024"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 21: | Line 21: | ||
** - About 1400 dividers have been fabricated (Chris, Armen, Mindy) | ** - About 1400 dividers have been fabricated (Chris, Armen, Mindy) | ||
** - Started removing power regulators on the newly fabricated dividers | ** - Started removing power regulators on the newly fabricated dividers | ||
− | ** - George has tested 54 dividers (919 have been tested in total) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. | + | ** - George has tested 54 dividers (919 have been tested in total) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. |
+ | ** - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers) | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] | ** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] |
Revision as of 09:18, 15 March 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV short cables: received, checked, labeled (last week)
- - HV long cable, 18 ready (out of 36)
- - HV distribution boards: in preparation
- - LV cables: 100 cables received, 500 cables in total
- - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
- Ongoing projects -- Sasha / Vlad / Hakob / Laveen
- - Tested and labeled all HV cables ! and about 100 LV cables
- - Bundling short cables (groups of 7, 7, and 6 cables)
- finished: LV - 7 layers, HV - 17 layers, signal - 4 layers
- Testing of PMT dividers -- Sasha / Vlad / George
- - Testing procedure [3]
- - About 1400 dividers have been fabricated (Chris, Armen, Mindy)
- - Started removing power regulators on the newly fabricated dividers
- - George has tested 54 dividers (919 have been tested in total) [4].
- - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Analysis/Simulation