Difference between revisions of "Run Coordination Meetings:Spring2025"
From GlueXWiki
m (→Hot Checkout) |
(→Hot Checkout) |
||
Line 304: | Line 304: | ||
'''To be completed by <font color="red"> TBD </font>''' | '''To be completed by <font color="red"> TBD </font>''' | ||
* [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=9&categoryId=401&systemId=®ionId=29&groupId=&qualified= Hot Check OUT Status] ( [https://cebaf.jlab.org/hco/reports/overall-status?destinationId=9&categoryId=401&systemId=®ionId=29&groupId=&qualified= Hot Check OUT Status (off site test version)]) | * [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=9&categoryId=401&systemId=®ionId=29&groupId=&qualified= Hot Check OUT Status] ( [https://cebaf.jlab.org/hco/reports/overall-status?destinationId=9&categoryId=401&systemId=®ionId=29&groupId=&qualified= Hot Check OUT Status (off site test version)]) | ||
− | <span style="color:green"> 37% ready </span>; <span style="color:#BABC3A">3% checked </span>; <span style="color:red"> | + | <span style="color:green"> 37% ready </span>; <span style="color:#BABC3A">3% checked </span>; <span style="color:red">60% not ready </span> |
==Readiness of subsystems for Spring 2025 run == | ==Readiness of subsystems for Spring 2025 run == |
Revision as of 11:43, 28 February 2025
Contents
- 1 Spring 2025 Run
- 2 Connect Information
- 3 Meeting General Agenda
- 4 Beam and Hall configuration
- 5 General Information
- 6 Runplan
- 7 Hall D situation room (current run plan)
- 8 Accelerator status
- 9 Hot Checkout
- 10 Readiness of subsystems for Spring 2025 run
- 11 Live Camera Feeds from the Four Counting Houses
- 12 Running Shifts Remote
Spring 2025 Run
Google Spreadsheet.
GlueX experiment (January 24 - July 20 2025)
Connect Information
To connect, please see the information on the GlueX meeting wikipage
Meeting General Agenda
Run planning meetings:
Beam and Hall configuration
- Commissioning of ECal.
- Other task that can be done if there are pauses in the ECal commissioning: see General_Information
- Commissioning of FCal.
- Experiment: GlueX-II/JEF.
- Beam energy expected:
- 12 GeV
- Beam polarization expected:
- from 5% to 73%, depending on other passes of the other Halls . No expectation of decent polarization before March 19th. Then 73% for the rest of the run.
- Solenoid:
- 1350A
- CW Beam:
- 250 MHz frequency.
- Range: 1na-1000 nA.
- Chopper slit: TBD
- Standard current and radiators
- 300 nA on a 4.1·10-4 R.L. radiator (50 μm diamond). (RSAD limit 400nA on 58 μm diamond))
- 300 on a 33.7·10-5 R.L. AL radiator (30 µm Al). (RSAD limit 480nA on 30 µm Al radiator))
- Position Slow Lock on or FFB on (FFB doesn't operate below 50nA).
- Radiators:
- Goniometer radiators: Start with JD70-107. Next, JD70-109. JD70-103 may still be usable if needed.
- Diamond JD70-107 (55 μm - 4.6·10-4 R.L., 7×7 mm²) New crystal. (Not expected to be great according to rocking curve.)
- Diamond JD70-109 (50 μm - 4.1·10-4 R.L., 7×7 mm² - New crystal - (Not expected to be good according to rocking curve.)
- Diamond JD70-103 (50 μm - 4.1·10-4 R.L., 7×7 mm²) Used in CPP. Partly spent.
- (Diamond JD70-106 (50 μm - 4.1·10-4 R.L., 7×7 mm²) - Aligned and used shortly during Tagger Accidental test in Spring 2020. Did not display sharp coherent peak.)
- (Diamond JD80-212 (80 μm - 6.6·10-4 R.L., 8×8 mm²) - To be tested.)
- (Diamond JD80-213 (80 μm - 6.6·10-4 R.L., 8×8 mm²) - To be tested.)
- Amorphous 40 μm Al radiator (44.9·10-5 R.L.)
- Amorphous 1.86·10-5 R.L., (for TAC run).
- Amorphous
- 1.64 µm Al (1.86·10-5 R.L., see study)
- 10 µm Al (11.2·10-5 R.L.)
- 30 µm Al (33.7·10-5 R.L.)
- Goniometer radiators: Start with JD70-107. Next, JD70-109. JD70-103 may still be usable if needed.
- Tagger quadrupole on (-4.2 A).
- Collimator hole: Default running: 5.0 mm.
- Targets:
- LH2 target: cryogenic target
- TPol converter: 75 μm
- Miscellaneous:
- PS test area. Tests must be fully opportunistic,without interfering with ECal commissioning and GlueX data taking. No more than 3 persons involved in such tests should be in the Hall during a control access:
- Presentations this Friday (01/17/2025):
- PS test area. Tests must be fully opportunistic,without interfering with ECal commissioning and GlueX data taking. No more than 3 persons involved in such tests should be in the Hall during a control access:
General Information
This document describes the run plan for the Hall D Spring 2025 run.
- Schedule for the run (see 2025 official schedule (draft)):
- February or March TBD: Electron beam restoration.
- January 24th - July 20th: 26 weeks for upgraded ECal commissioning and GlueX-II/JEF. As of 02/25/25, 9 weeks shift ⇒ March. 21st - Sept. 15th ?
- Accelerator overall plan and priorities: Deliver physics beam to 4 halls
- Hall D plan summary:
- Beam and detector check-out: 50 - 300 nA. ~ a day.
- Commission new beam profiler from Regina (Hovanes).
- Commission of ECal (~ a month. 150 nA)
- Opportunistic tests during possible pauses of ECAL Commissioning:
- Diamond alignment (Hovanes, see below)
- CDC HV scans (Beni, Naomi). Need compatible trigger
- ToF HV scans (Beni). Need compatible trigger
- Lead glass HV scans (Malte). Need compatible trigger
- Study thick 80μm new diamond (Richard).
- Others?
- Opportunistic tests during possible pauses of ECAL Commissioning:
- Commissioning of FCal (In parallel with ECal. Needs a commissioning plan.)
- Diamond alignment: Stable beam (no frequent trip) 20 nA without FSD for 2-3 shifts.
- Experiment: GlueX-II/JEF E12-12-002
- 2 TAC runs. ~nA or less. The bleedthrough should be small compare to it. 1 run just after ECAL Commissioning. Another near the end of the run.
- Ideally, TAC run should be done with the other Halls off.
- If not possible, the next best option is to have both A and C not at 5 passes, so that magnetic extraction is performed (less bleedthrough than with RF separation).
- Either Hall A or C or both are at 5 passes during the whole run ⇒ we will have to watch for opportunity when the Hall at 5 passes is down.
- High luminosity runs: up to 1 week at 650nA, and up to 1 day at 1 uA.
- 2 empty target runs (300 nA). 1 run at the start of GlueX-II data taking. Another near the end of the run.
- Straight track run: 2 shifts (50% efficiency: one shift of good data) (50 nA on 10-4 R.L. radiator).
- Opportunistic tests:
- GEM-TRD test during ECAL Commissioning Positioned 3 to 6 o'clock in front of forward detectors, looking downstream.
- Beam and detector check-out: 50 - 300 nA. ~ a day.
- Expected Staffing and responsibilities:
- The Run Coordinator oversees the run:
-
Jan. ?? - ??, ?? days (beam restoration): Alexandre Deur - Jan. 24 - 29, 6 days: Alexandre Deur
- Jan. 29 - Feb. 5, 1 week: Igal Jaegle
- Feb. 5-12, 1 week: Simon Taylor
- Feb. 12-19, 1 week: Edmundo Barriga
- Feb. 19-26, 1 week: Colin Gleason
- Feb. 26-March 5, 1 week: Igal Jaegle
- March 1-5 5 days: Alexandre Deur
- March 5-12, 1 week: Simon Taylor
- March 12-19, 1 week: Igal Jaegle
- March 19-26, 1 week: Alexandre Deur
- March 26-Apr. 2, 1 week: Igal Jaegle
- Apr. 2-9, 1 week: Naomi Jarvis
- Apr. 9-16, 1 week: Mark Dalton
- Apr. 16-23, 1 week: Hao Li
- Apr. 23-30, 1 week: Mike McCaughan
- Apr. 30-May 7, 1 week: Alexandre Deur
- May 7-14, 1 week: Richard Jones
- May 14-21, 1 week: Justin Stevens
- May 21-28, 1 week: Boris Grube
- May 28-June 4, 1 week: Amy Schertz
- June 4-11, 1 week: Edmundo Barriga
- June 11-18, 1 week: Naomi Jarvis
- June 18-25, 1 week: Drew Smith
- June 25-July 2, 1 week: Hao Li
- July 2-9, 1 week: Simon Taylor
- July 9-16, 1 week:
- July 16-23, 1 week: Mark Dalton
- July 23-30, 1 week: Alexandre Deur
- July 30-Aug. 6, 1 week: Mike McCaughan
- Aug. 6-13, 1 week: Colin Gleason
- Aug. 13-20, 1 week: Simon Taylor
- Aug. 20-27, 1 week: Edmundo Barriga
- Aug. 27-Sept. 3, 1 week: Boris Grube
- Sept.3-10, 1 week: Drew Smith
- Sept.10-15, 6 days: Igal Jaegle
-
- The Run Coordinator oversees the run:
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (S. Spiegel) verify that the proper safety rules are followed. PDL is:
- PDL: B.Zihlmann
- The analysis coordinator (Alexander Austregesilo) oversees the off-line diagnostic of the different systems and analysis of the data.
- Shifts: 2 person shifts: 1 leader and 1 worker, both on-site, scheduled through the GlueX shift scheduler.
- Coordination Activities:
- The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
- Run meetings: broadcasted on Zoom. 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
- Useful links:
- Accelerator schedule and information
- Link to Richard Jones program to plot the beam profile at the collimator.
- Links to previous runplans
- Web-accessible EPICS information
- Links to beam parameters/radiation level monitoring:
- Last 8-hours plots showing 1-minute, 10-minute, and hourly averages
- Same but Last 24-hours
- Same but Last 72-hours
- Week, month, and quarter (3 months) plots also exist, with similar web addresses.
- A map of the radiation monitors
Runplan
Hall D situation room (current run plan)
Hall D counting room white board
Accelerator status
- Link to accelerator short term schedule (White board)
- Link to accelerator SAD calendar
- Bluejeans code for the daily MCC meetings and Wednesday 1:30 meeting: 569476853
Hot Checkout
To be completed by TBD
37% ready ; 3% checked ; 60% not ready
Readiness of subsystems for Spring 2025 run
(This section is commented out for clarity)
Live Camera Feeds from the Four Counting Houses
- These feeds SHOULD be open and visible at all times from one of the monitors in each of the counting houses.
- Management cautions AGAINST opening them from other locations or offsite, out of concern for available bandwidth.
- Beni will contact Walt Akers to inquire about their status. Done. Walt will take care of it.