# Electron Commissioning (Todd/Mike) | # Electron Commissioning (Todd/Mike) | ||
# Photon Commissioning Draft (Eugene) | # Photon Commissioning Draft (Eugene) | ||
− | # | + | # Aug 8 Review: Location CC L102 |
+ | #* Reviewers: Mike Spata, Brian Freeman, Stepan Stepanyan | ||
+ | #* Materials: Accelerator Procedures (Mike); Plan for photon beam commissioning (?) | ||
+ | #* Talks: Photon beam properties (Richard); Electron beam commissioning (Todd); Photon beam commissioning (?) | ||
# Other business | # Other business | ||
Revision as of 15:39, 16 July 2014
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
- Hall D Commissioning Pages
- DRAFT Accelerator Hall D Beam Delivery Procedures(V.1b9)
- DRAFT Accelerator Tagger Magnet Operation Procedures(V. 0)
- DRAFT Accelerator Hall D Ion Chamber Functional Test Procedure(V.1b3)
- DRAFT Accelerator Hall D Ion Chamber Calibration Procedure(V.1b2)
Action Items
-
Send link to accelerator commissioning procedure (Mike) - Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard)
- Todd will provide the magnetic field of the quadrupole immediately upstream of the tagger magnet (Todd)
- Check that radiator set for commissioning is available (Alexandre, Hovanes)
- Check that RadCon detectors are available/installed in tagger hall and hall D (Alexandre)
- Check that 'rapid access system' is being implemented in Hall D (Alexandre)
- Organize preparations for review (Elton).
Agenda
- Announcements
- Electron Commissioning (Todd/Mike)
- Photon Commissioning Draft (Eugene)
- Aug 8 Review: Location CC L102
- Reviewers: Mike Spata, Brian Freeman, Stepan Stepanyan
- Materials: Accelerator Procedures (Mike); Plan for photon beam commissioning (?)
- Talks: Photon beam properties (Richard); Electron beam commissioning (Todd); Photon beam commissioning (?)
- Other business
Minutes
- Attending: