JEF meeting, February 16, 2024
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 165 cables 1445 in total
- - HV distribution boards: in preparation
- - LV cables: 100 cables received, 250 cables in total
- - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
- - Optical fibers and parts for the trigger/DAQ have been ordered
- Ongoing projects -- Sasha, all
- - Testing and labeling cables, 100 short LV cables tested and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Radiation tests of the PMT active base [5]
- Finished tests, working on the tech note
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / George
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
- Analysis/Simulation