Run Planning Meeting Notes, September 8 - September 14, 2022
From GlueXWiki
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Thursday, September 8
Past 24 hours
- Maintenance day
- Work done in hall:
- Removed Be target, Installed He target and ramped magnet:
- Fixed connection for missing channels in ST:
- Replaced FCAL bases & one PMT (Malte): [1], [2]
- LHe Target full and ready after ~11 hours, [3]
- Extrapolations from harp scans
- FCAL HV Correction for outliers
- 308M Triggers collected while target was filling and solenoid ramping.
- 404M Triggers collected with target full and solenoid ramped.
- More details can be found here
Issues
- FDC-RF selftiming peak is missing
- Hall C will do BCM calibrations this afternoon, coordinate access to fix FDC TDCs with this?
Plan
- Rate+Trigger Studies (Sasha)
- Begin(continue) production on LHe Target @200nA