Run Planning Meeting Notes, September 8 - September 14, 2022
From GlueXWiki
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Friday, September 9
Past 24 hours
- Production data at 200nA on the liquid He target.
- FCAL HV Scan with solenoid field on
- Trigger studies and rate scan performed by Sasha
- Added low-threshold trigger for FCAL (0.5GeV Trigger threshold)
- 2 noisy FCAL channels were masked
- Beam stability on the active collimator (Beni)
- Shift summaries:
- 0400-1000 09/09
- 2200-0400 08/09-09/09
- 1600-2200 08/09
- 1000-1600 08/09
- 0400-1000 08/09
Issues
- Beam was unavailable for about 1 hour during the day shift due to Hall C's BCM calibration. We correlated the FCAL HV scan with this downtime.
- Minor issue with one shift worker not showing up. Thanks to Karthik for taking that role on short notice.
Plan
- Continue taking production data at 200nA.
- PrimEx Run Plan
Thursday, September 8
Past 24 hours
- Maintenance day
- Work done in hall:
- Removed Be target, Installed He target and ramped magnet:
- Fixed connection for missing channels in ST:
- Replaced FCAL bases & one PMT (Malte): [1], [2]
- LHe Target full and ready after ~11 hours, [3] (Chris Carlin)
- Extrapolations from harp scans
- FCAL HV Correction for outliers (Igal)
- 308M Triggers collected while target was filling and solenoid ramping.
- 404M Triggers collected with target full and solenoid ramped.
- More details can be found here
Issues
- FDC-RF selftiming peak is missing
- Hall C will do BCM calibrations this afternoon, coordinate access to fix FDC TDCs with this?
Plan
- Rate+Trigger Studies (Sasha)
- Begin(continue) production on LHe Target @200nA
- Wednesday, 9/14: MCC plans to open the tunnel with the goal to bring up as much RF as possible. They plan to spend ~1.5 shifts for this.