JEF meeting, May 5, 2023
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Crystals:
- Received 30 crystals from CRYTUR [1]. Remaining 65 crystals will be sent to us during this and next month.
- Wrapped crystals ready for fabrication (Mindy): 26 SICCAS and 5 CRYTUR = 31
- Available for wrapping: 10 SICCAS + 28 CRYTUR = 38
- George (DSG group) preshaped 96 ESR reflectors; finished with preshaping.
- More than 200 long signal cables received, can start checking, bundling, labeling
- Procurement parts for the LMS
- Ordered 16,000 ft of optical fibers. Expect that they will be delivered in May. Adding additional 8000 ft to the PO
- Ordered 18000 of polycarbonate donats
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1487
- Available for fabrication: 26
- Fabricate 36 modules using 'low quality' crystals for stacking mockup and 'crash' tests (train students on them)
- Fabricated modules: Total 1487
- Testing of PMT dividers -- Sasha / Vlad / Arshak
- FCAL2 modules with dividers installed on the CCAL [2]
- Met with Vlad P. on Tuesday. Fine tuned the divider circuit (modified some resistors). Chris S. ordered new parts
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [3]
- Discussion of the FCAL2 installation procedures [4]
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light Monitoring System -- Arshak
- Preparation of parts for FCAL2 modules -- Sasha
- Module fabrication -- Sasha
- PMT divider updates
- Light Monitoring System -- Arshak
- Simulations/Analysis
- GUINEAPIG Workshop?