JEF meeting, October 4, 2024
From GlueXWiki
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- - 5 (12 x 4) and 5 (6 x 8) boards have been received. Received all PCB boards. Soldering wires to connectors (one distribution board is ready, one more board will be ready during next week)
- - Sent out request of quotes for HV board boxes
- - Consider to build temporarry boxes for testing
- - Two panels for the LV distribution boards received, need to re-connect cables (Sasha, Laveen, Vlad) [3]
Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Installation of the light distribution board of the ECAL LMS [4]
- - Fine-tune the light source
- Implementing ECAL into the GlueX DAQ [5]
- - rocecal3 crate was fixed [6] (initial DAQ implementation [7])
- - implementing flash ADC scalers [8]
- - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [9]
- - implementing and verifying ECAL LMS trigger [10]
- - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [11]
- - Installation of scintillating paddles for cosmic tests [12]
- Detector installation page
- Safety briefings
- Meeting with Drew Weisenberger regarding Vlad'd involvement in commissioning
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Connecting cooling pipes to the ECAL fan (done by tech group)
- - Installing dark room ceiling and insulation inside the room, required for cooling test (next week)
- - Test cooling system (next week)
- - Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)
Students -- Sasha
- Zhikun arrived to the lab
Restoring PS test setup [13]
ECAL commissioning -- Sasha, All