Photon Beam Commissioning Discussion July 23, 2014
From GlueXWiki
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
- Hall D Commissioning Pages
- DRAFT Accelerator Hall D Beam Delivery Procedures(V.1b9)
- DRAFT Accelerator Tagger Magnet Operation Procedures(V. 0)
- DRAFT Accelerator Hall D Ion Chamber Functional Test Procedure(V.1b3)
- DRAFT Accelerator Hall D Ion Chamber Calibration Procedure(V.1b2)
Action Items
- Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this
- Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Alexandre for Hall D)
Agenda
- Announcements
- Electron Commissioning (Todd/Mike)
- Hall D Beam Delivery Procedure heading to Rev. 10 with feedback received.
- Ion Chamber Procedures currently under review for release for use.
- Eugene/Curtis added as administrators for Hall D Operational Restrictions[1]
- System Experts requested to write test plans for nA BPM, FFB, and Active Collimator hardware commissioning.
- Cross Calibration Procedure for absolute current measurement desired?
- Point of contact in Radcon for measurement test plan for fall? (George or Pavel perhaps?)
- Regarding minimum deliverable current: {| class="wikitable" style="text-align: center; color: black;"
|Stripline BPM Resolutions |≥ 30nA 100um resolution |< 30nA resolution suffers(position noisy barring additional filtering) |3nA yields expected resolution ≈ 300 µm |}
- Photon Commissioning Draft (Alexandre)
- Radiation monitors
- Aug 8 Review:
- Other business
Minutes
Attending:'