Agenda

Preparation of parts for ECAL -- Sasha

Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

Preparing for the run -- Sasha

  • Trouble shooting [1]

Restoring PS test setup [2]

  • Moving CCAL box to EEL126
  • Testing ECAL modules using LMS
  • Will get 25 LG modules from Malte during next week

ECAL commissioning -- Sasha, All

Calibrations

Minutes

Attendees: Mac, Zisis, Sasha, Hakob, Liping, Jane, Drew, Axel, Olga, Igal, Bill, S.T.

  • Everything for LMS system in place
    • Light source and alpha source in trigger
    • Used LMS to check detector, found a few problematic channels in ECAL --> fixed loose connections
      • Some channels have funny waveforms, some have low amplitudes (likely due to fibers)
  • Amplification on on 1 ECAL channel fluctuating -> swapped divider, now fixed
  • Found distribution board problem -> reroute to spare channel
  • Temperature trip due to fan not being in same place as before?
  • Progress on small scale prototype
    • Verified 5x5 PWO + 5x4 lead glass will fit inside COMCAL box
    • Have 2 chillers that can be used to maintain temperature and study temperature dependence
    • Will move effort to EEL126, testing using LED setup in EEL118
    • Lead glass modules will be provided by Malte
    • Plan for test in PS arm in summer
  • Commissioning plan
    • Start with voltages set from cosmic runs
    • Set up trigger starting with sub-detectors, run at small flux and low thresholds
    • Use Compton events to tune ECAL voltages near beam line
      • Adjust channels to same scale in FADC
    • Will ID bad channels in lead glass region to exclude
    • Use π0 events to refine