JEF meeting, April 12, 2024

From GlueXWiki
Revision as of 09:21, 12 April 2024 by Somov (Talk | contribs)

Jump to: navigation, search

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV short cables: received, checked, labeled (last week)
    • - HV long cable, 18 ready (out of 36)
    • - HV distribution boards: in preparation
    • - LV cables: waiting for about 440 cables (will need to test, label, and bundle)
    • - LV distribution boards [2]. Have to populate with connectors, and design a box around the PCB
  • Ongoing projects
    • - Bundling short cables (groups of 7, 7, and 6 cables): signal (done), HV (done), LV (29 layers done, waiting for cables)
    • - Testing, labeling, and bundling LV cables [3] [4]
  • Testing of PMT dividers -- Sasha / Vlad / George / Mindy
    • - Testing procedure [5]
    • - Mindy has finished with preparing all sockets (~1650) !
    • - All dividers have been fabricated
    • - Need to remove power regulators on about 200 dividers
    • - George has tested about 1400 dividers [6].
    • - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
    • All ePASes are ready for the installation -- Sasha and Vlad
      • - need to prepare one for testing dividers and maintenance
    • Installation of the LMS
      • 1325 fibers have been installed [7]
    • Cable and divider installation [8][9][10]
    • Bundles with optical fibers for the trigger have been installed (Chris, Armen, Mark). Need to install 2 patch panels
    • Receive optical network fibers. Will install them as well as the network switch during next week
    • 7 VXS controllers can be booted now
    • Detector installation page
    • Other hardware projects
      • --prototype of the ECAL veto counter
      • --study shower profile using PS (also transition region between lead tungstate and LG modules (?) )
  • Analysis/Simulation
  • FCAL2 poster for open house?
    • JEF/ECAL/FCAL poster
    • exhibit stand (modules, PMTs, etc.)