Difference between revisions of "JEF meeting, December 15, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 8: Line 8:
 
** - signal cables -  done
 
** - signal cables -  done
 
** - signal patch [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done
 
** - signal patch [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done
** - HV cables: received 165 short cables during this week
+
** - HV cables: received 165 short cables during this week (965 in total)
 
** - HV distribution boards: in preparation
 
** - HV distribution boards: in preparation
 
** - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January   
 
** - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January   

Revision as of 17:14, 14 December 2023

eeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch [1] - done
    • - HV cables: received 165 short cables during this week (965 in total)
    • - HV distribution boards: in preparation
    • - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January
    • - LV distribution boards. In production
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [11]
    • - Tested 420 dividers [12]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob