JEF meeting, December 15, 2023

From GlueXWiki
Revision as of 17:16, 14 December 2023 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

eeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel[1] - done
    • - HV cables: received 165 short cables during this week (965 in total)
    • - HV distribution boards: in preparation
    • - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January
    • - LV distribution boards. In production
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables [2], 80 short HV cables testes and labeled during this week.
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections)