JEF meeting, December 15, 2023

From GlueXWiki
Revision as of 18:34, 14 December 2023 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

eeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel[1] - done
    • - HV cables: received 165 short cables during this week (965 in total)
    • - HV distribution boards: in preparation
    • - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January
    • - LV distribution boards. In production
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables [2], 80 short HV cables testes and labeled during this week.
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
      • 26 modules for TAC and 35 modules for the beam tests are ready
    • - Preparation of the LMS
      • - All fibers are ready for the installation [3]
      • - Installing light-tight covers on the plastic caps [4][5][6][7] Installed 1245 covers.
      • - Received bench for the integrating sphere; machined to the right size [ ]
    • - Radiation tests of the PMT active base [8]
    • - https://halldweb.jlab.org/detectors/AL/HallD_Racks/
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [9]
    • - Tested 420 dividers [10]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob