(Agenda)
 
(8 intermediate revisions by one other user not shown)
Line 18: Line 18:
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals] - done
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/wrapped_modules.jpg Wrapped crystals] - done
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] - done
 
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac.jpg Parts for TAC][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/parts_for_tac1.jpg] - done
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Modules for prototype (25 are ready)] - done
+
*** [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_20_2023/modules_for_prototype.jpg  Prepared 26 modules for TAC and 35 modules for beam tests] - done
 
** -  Preparation of the LMS  
 
** -  Preparation of the LMS  
 
*** - All fibers are ready for the installation. The plate was machined and polised [https://logbooks.jlab.org/entry/4228633]
 
*** - All fibers are ready for the installation. The plate was machined and polised [https://logbooks.jlab.org/entry/4228633]
*** - Installing light tight covers on the plastic caps.  
+
*** - Installing light tight covers on the plastic caps [https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt4.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt3.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt1.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt2.jpg]
 +
*** - Meeting with Fernando and Chris regarding LED drivers
 
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran / Boaxin
+
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran  
 
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]
 
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]
 
** - Tested 420 dividers [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]
 
** - Tested 420 dividers [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]
Line 30: Line 31:
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey]  
 
** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey]  
 +
*** - waiting for survey results
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 
** Meeting with Chris Cuevas regarding installing optical fibers and patch panels
 
** Meeting with Chris Cuevas regarding installing optical fibers and patch panels
 +
** Installation of electronics [https://halldweb.jlab.org/wiki/index.php/FCAL2_Crates]
 
* '''[[Lead Glass Efforts]]''' -- Malte / Mark / Kevin / Zisis
 
* '''[[Lead Glass Efforts]]''' -- Malte / Mark / Kevin / Zisis
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''
 +
 +
=Minutes=
 +
Attendees: Liping, Sasha, Igla, Aoran, Stjepan, Zisis, Olga, Jane, Jon. S. T.
 +
* All signal cables ready, have half of short HV cables, long HV cables in production
 +
* LV distribution board design finalized, boards ordered (2 week lead time + 1 week to populate)
 +
* Waiting for LV cables -- received first article
 +
* LMS fibers glued to moujutinge plate, in process making everything light tight
 +
* Met with Fernando regarding LED pulser
 +
** Use one port in integrating sphere to inject light
 +
** Use CAEN1495 module to generate pulse
 +
* PMT divider tests continue
 +
* PMT divider radiation tests completed (total expoasure = 50 kRad)
 +
** Amplitude degrades with dose
 +
* Made visual inspection of FCAL, taking note of location of shims
 +
** Also looking for bubbles in cookie interface -- may need retorquing
 +
** Found one suspicious PMT -- practice removal?
 +
* Requested survey of FCAL-2 perimeter
 +
* No power on FCAL platform yet, expected in January
 +
* Optical fibers for DAQ will be installed in January/February
 +
* Magnetic shielding for reference PMTs for LMS system will be needed
 +
* Installation of plexiglas for lead glass LMS system underway
 +
* Fiber LMS system for insert will be installed in January, then installation of cables, PMT dividers, etc. will take 3-4 months
 +
* Expecting beam profiler from U.Regina in January, to replace existing rad-damaged profiler
 +
** Maybe could refurbish old profiler to use for shower profile measurements
 +
* Plan to build 5x5 ECAL array with some LG surrounding, measure properties in transition region

Latest revision as of 09:09, 11 December 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
    • - signal patch panels are ready [1]
    • - HV cables: 800 cables are ready for installation. Long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The LV distribution boards have been ordered.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [11]
    • - Tested 420 dividers [12]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Lead Glass Efforts -- Malte / Mark / Kevin / Zisis
  • Analysis/Simulation

Minutes

Attendees: Liping, Sasha, Igla, Aoran, Stjepan, Zisis, Olga, Jane, Jon. S. T.

  • All signal cables ready, have half of short HV cables, long HV cables in production
  • LV distribution board design finalized, boards ordered (2 week lead time + 1 week to populate)
  • Waiting for LV cables -- received first article
  • LMS fibers glued to moujutinge plate, in process making everything light tight
  • Met with Fernando regarding LED pulser
    • Use one port in integrating sphere to inject light
    • Use CAEN1495 module to generate pulse
  • PMT divider tests continue
  • PMT divider radiation tests completed (total expoasure = 50 kRad)
    • Amplitude degrades with dose
  • Made visual inspection of FCAL, taking note of location of shims
    • Also looking for bubbles in cookie interface -- may need retorquing
    • Found one suspicious PMT -- practice removal?
  • Requested survey of FCAL-2 perimeter
  • No power on FCAL platform yet, expected in January
  • Optical fibers for DAQ will be installed in January/February
  • Magnetic shielding for reference PMTs for LMS system will be needed
  • Installation of plexiglas for lead glass LMS system underway
  • Fiber LMS system for insert will be installed in January, then installation of cables, PMT dividers, etc. will take 3-4 months
  • Expecting beam profiler from U.Regina in January, to replace existing rad-damaged profiler
    • Maybe could refurbish old profiler to use for shower profile measurements
  • Plan to build 5x5 ECAL array with some LG surrounding, measure properties in transition region