JEF meeting, December 8, 2023

From GlueXWiki
Revision as of 10:01, 8 December 2023 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
    • - signal patch panels are ready [1]
    • - HV cables: have received 330 short cables, have been testes and labeled. 800 cables are ready for installation. Long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The design of the LV distribution board has been finalized. Boards will be ordered during next week.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
    • - Testing procedure [7]
    • - Tested 420 dividers [8] (104 last week)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob




  • Preparation of parts for ECAL -- Sasha
  • Ongoing projects -- Sasha, all
    • - Preparation of the LMS
  • Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Lead Glass Efforts -- Malte / Mark / Kevin / Zisis
  • Analysis/Simulation