JEF meeting, December 8, 2023

From GlueXWiki
Revision as of 10:13, 8 December 2023 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: Received all needed long cables. Redid and tested 4 bundles. All cables are ready.
    • - signal patch panels are ready [1]
    • - HV cables: 800 cables are ready for installation. Long cables are in production
    • - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards. The LV distribution boards have been ordered.
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [7]
    • - Tested 420 dividers [8]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Lead Glass Efforts -- Malte / Mark / Kevin / Zisis
  • Analysis/Simulation