(Agenda)
Line 17: Line 17:
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
 
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
 
***  26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg]  and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready
 
***  26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg]  and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready
** -  Preparation of the LMS
 
*** - Need to glue Al flange to the optical fiber
 
*** - Ready for installation [https://halldweb.jlab.org/detectors/fcal2/lms/installation]
 
 
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
*** Finished tests, working on the tech note
 
*** Finished tests, working on the tech note

Revision as of 10:19, 9 February 2024

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received 165 cables 1445 in total
    • - HV distribution boards: in preparation
    • - LV cables: 100 cables received, 250 cables in total
    • - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
    • - Optical fibers and parts for the trigger/DAQ have been ordered
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / George
    • - Testing procedure [6]
    • - Tested 637 divider (all fabricated dividers) [7]. No dividers produced during this week.
    • - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
    • Detector installation [8][9][10]
    • Installation of the LMS
      • 127 fibers installed during this week (313 in total) [11]
    • Cable and divider installation [12]
    • Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
    • Detector installation page