* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George
 
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]
 
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]
** - Tested 637 divider (all fabricated dividers) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. No dividers produced during this week.
+
** - ePASS submitted and approved
 +
** - Tested 637 + 41 = 678 dividers (about 30 available for testing) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers].  
 
** - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
 
** - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad  
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad  

Revision as of 10:23, 9 February 2024

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received 165 cables 1445 in total
    • - HV distribution boards: in preparation
    • - LV cables: 100 cables received, 250 cables in total
    • - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [2]
    • - Optical fibers and parts for the trigger/DAQ have been ordered
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad / George
    • - Testing procedure [6]
    • - ePASS submitted and approved
    • - Tested 637 + 41 = 678 dividers (about 30 available for testing) [7].
    • - Spare PMTs, have about 20, likely need more for the future (order 30 more )?
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad
    • Detector installation [8][9][10]
    • Installation of the LMS
      • 127 fibers installed during this week (313 in total) [11]
    • Cable and divider installation [12]
    • Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
    • Detector installation page