Difference between revisions of "JEF meeting, January 19, 2024"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 14: | Line 14: | ||
** - LV cables: received first article of short cables, production started on Dec. 7, have not received yet. | ** - LV cables: received first article of short cables, production started on Dec. 7, have not received yet. | ||
** - LV distribution boards. In production | ** - LV distribution boards. In production | ||
+ | ** - Optical fibers and parts for the trigger/DAQ have been ordered | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
** - Testing and labeling cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ], 120 short HV cables testes and labeled during this week. | ** - Testing and labeling cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ], 120 short HV cables testes and labeled during this week. | ||
Line 32: | Line 33: | ||
** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey] | ** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey] | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
− | |||
** Meeting with Chris Cuevas regarding installing optical fibers and patch panels | ** Meeting with Chris Cuevas regarding installing optical fibers and patch panels | ||
** Installation of electronics [https://halldweb.jlab.org/wiki/index.php/FCAL2_Crates] | ** Installation of electronics [https://halldweb.jlab.org/wiki/index.php/FCAL2_Crates] | ||
* [https://halldweb.jlab.org/wiki-private/index.php/GlueX_April_APS_2024 Abstracts for April'24 APS meeting] | * [https://halldweb.jlab.org/wiki-private/index.php/GlueX_April_APS_2024 Abstracts for April'24 APS meeting] |
Revision as of 09:45, 19 January 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 165 short cables during this week (1280 in total)
- - HV distribution boards: in preparation
- - LV cables: received first article of short cables, production started on Dec. 7, have not received yet.
- - LV distribution boards. In production
- - Optical fibers and parts for the trigger/DAQ have been ordered
- Ongoing projects -- Sasha, all
- - Testing and labeling cables [2], 120 short HV cables testes and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Preparation of the LMS
- - Need to glue Al flange to the optical fiber
- - Ready for installation
- - Radiation tests of the PMT active base [5]
- Finished tests, working on the tech note
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [8][9][10]
- Detector survey
- Detector installation page
- Meeting with Chris Cuevas regarding installing optical fibers and patch panels
- Installation of electronics [11]
- Abstracts for April'24 APS meeting