Difference between revisions of "JEF meeting, January 19, 2024"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 34: Line 34:
 
*** Started yesterday (after long delay)[https://halldweb.jlab.org/detectors/fcal2/lms/installation/ready_to_install2.jpg] [https://halldweb.jlab.org/detectors/fcal2/lms/installation/ready_to_install1.jpg]
 
*** Started yesterday (after long delay)[https://halldweb.jlab.org/detectors/fcal2/lms/installation/ready_to_install2.jpg] [https://halldweb.jlab.org/detectors/fcal2/lms/installation/ready_to_install1.jpg]
 
*** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
 
*** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
 +
** Cable and divider installation
 +
*** Started yesterday, making a decision how to stretch them [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/01_19_2024/cables_start_to_install.jpg]
 
** Still no power on the ECAL platform  (expect delay with the development of the trigger/DAQ)
 
** Still no power on the ECAL platform  (expect delay with the development of the trigger/DAQ)
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
  
 
<!-- ** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey] -->
 
<!-- ** [https://halldweb.jlab.org/wiki/index.php/Detector_Alignment Detector survey] -->

Revision as of 10:18, 19 January 2024

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received 165 short cables during this week (1280 in total)
    • - HV distribution boards: in preparation
    • - LV cables: received first article of short cables, production started on Dec. 7, have not received yet.
    • - LV distribution boards. In production
    • - Optical fibers and parts for the trigger/DAQ have been ordered
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables [2], 120 short HV cables testes and labeled during this week.
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
      • 26 modules for TAC [3] and 35 modules [4] for the beam tests are ready
    • - Preparation of the LMS
      • - Need to glue Al flange to the optical fiber
      • - Ready for installation
    • - Radiation tests of the PMT active base [5]
      • Finished tests, working on the tech note
    • - Inventory database and GUI for installed electronics
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [6]
    • - Tested 637 divider (all fabricated dividers) [7]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
    • Detector installation [8][9][10]
    • Installation of the LMS
      • Started yesterday (after long delay)[11] [12]
      • Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
    • Cable and divider installation
      • Started yesterday, making a decision how to stretch them [13]
    • Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
    • Detector installation page