JEF meeting, January 19, 2024

From GlueXWiki
Revision as of 10:18, 19 January 2024 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received 165 short cables during this week (1280 in total)
    • - HV distribution boards: in preparation
    • - LV cables: received first article of short cables, production started on Dec. 7, have not received yet.
    • - LV distribution boards. In production
    • - Optical fibers and parts for the trigger/DAQ have been ordered
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables [2], 120 short HV cables testes and labeled during this week.
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
      • 26 modules for TAC [3] and 35 modules [4] for the beam tests are ready
    • - Preparation of the LMS
      • - Need to glue Al flange to the optical fiber
      • - Ready for installation
    • - Radiation tests of the PMT active base [5]
      • Finished tests, working on the tech note
    • - Inventory database and GUI for installed electronics
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [6]
    • - Tested 637 divider (all fabricated dividers) [7]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
    • Detector installation [8][9][10]
    • Installation of the LMS
      • Started yesterday (after long delay)[11] [12]
      • Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)
    • Cable and divider installation
      • Started yesterday, making a decision how to stretch them [13]
    • Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
    • Detector installation page